Shanahan Engineering Ltd

Shanahan Engineering Ltd

Lead Planning Engineer, Shanahan Engineering Ltd, PP-12 Power Station, Riyadh, SA

START Date
END Date
Experience Hours (Planning & Scheduling)
1400
Experience Hours (Cost Management)
150
Experience Hours (Forensic Analysis)
300

I was Lead planning engineer for Shanahan Engineering working on the short term commissioning programme of block 2 of the 2.2gw CCGT PP-12 power station 140km west of Riyadh, total make up across the plant of 8 Gas Turbines, 8 HRSG’s & 2 Steam Turbine’s.

 

Lead Planning Engineer, Shanahan Engineering Ltd, 900MW CCGT Power Station Construction - Israel

START Date
END Date

Pre-site initial baseline production & full live project contract planning works for an 800MW 12 Gas Turbine, 12 OTSG & 2 Steam Turbine power plant construction in the middle east.