Samsung Engineering & Construction

Samsung Engineering & Construction

Project Engineer, Samsung Engineering & Construction, Saudi kayan Jubail, Riyadh Clean Transport Fuel CO2 projects

START Date
END Date
Experience Hours (Planning & Scheduling)
3000

1.   Worked as Project Engineer (Project Management Dept.) with Samsung Engineering Saudi Arabia in Kingdom of Saudi Arabia.

×    Responsible to review the design engineering activities and specifications of all mechanical, Steel Structural design, according to the requirements of the project, carried out by Vendors/ Subcontractors in all areas according to national and international Codes and Standards.

Project Engineer, Samsung Engineering & Construction, Saudi kayan Jubail, Riyadh Clean Transport Fuel CO2 projects

START Date
END Date
Experience Hours (Planning & Scheduling)
3000

1.   Worked as Project Engineer (Project Management Dept.) with Samsung Engineering Saudi Arabia in Kingdom of Saudi Arabia.

×    Responsible to review the design engineering activities and specifications of all mechanical, Steel Structural design, according to the requirements of the project, carried out by Vendors/ Subcontractors in all areas according to national and international Codes and Standards.

Asst. Planning Engineer, Samsung Engineering & Construction, A variety of oil and gas and engineering projects.

START Date

Career objective
Position – Planning Engineer
Work Experience (2.0 year)
PLANNING ENGINEER
July 2010 to Dec-2011
Engineers India Limited
SRU (Sulphur Recovery Plant), P III Project, MRPL, Mangalore
PLANNER
Jan 2012 to till date
Samsung Engineering Company Limited (Saudi Arabia)
Saudi Basic Industries Corporation (SABIC)

Responsibilities:
 Preparation of detailed planning schedules for the project.
 Compilation of progress data for daily, weekly & monthly progress reports.
 Preparation of Daily, Weekly & Monthly progress reports.
 Update Engineering register for deliverab

Asst. Planning Engineer, Samsung Engineering & Construction, A variety of oil and gas and engineering projects.

START Date

 

Career objectivePosition – Planning EngineerWork Experience (2.0 year) PLANNING ENGINEERJuly 2010 to Dec-2011Engineers India LimitedSRU (Sulphur Recovery Plant), P III Project, MRPL, Mangalore PLANNERJan 2012 to till dateSamsung Engineering Company Limited (Saudi)Saudi Basic Industries Corporation (SABIC)

Planning Engineer, Samsung Engineering & Construction, Al Salam Street Tunnel Project

START Date

- Identify Delay Events.

- Preparation of Delay Notices as per Contract Clauses.

- Preparation of As Built Program.

- Preparation of Fragnet Programs.

- Preparation of Extension of Time Program.

- Negotiating Time Claim with Clients.

- Preparation of Claims Narrative.

- Identifying Concurrency Issues in the Program.

- Identifying Possible Mitigation Measures.