Rizzani De Eccher

Rizzani De Eccher

Amr Diab

A
Amr Diab 👤 Member for 19 years 4 months
First Name
Amr
Last Name
Diab
Professional Since
Oldest experience
Years Experience
43

Planner/Scheduler, Rizzani De Eccher, Tajik Afghan Bridge, Delhi Metro Rail Project

START Date
END Date

Project Control Engineer reporting to the Branch Manager. Performed planning and scheduling, prepared schedule of works, and reports for client and consultant submission.  Reporting included schedule status and progress, schedule look ahead, s-curve man-hour analysis of forecast versus actual, and mitigation plans to recover schedule delays. Prepared monthly invoices and weekly/monthly progress reports. Organized and controlled material procurement schedule to expedite material deliveries.

Planner/Scheduler, Rizzani De Eccher, Tajik Afghan Bridge, Delhi Metro Rail Project

START Date
END Date

Project Control Engineer reporting to the Branch Manager. Performed planning and scheduling, prepared schedule of works, and reports for client and consultant submission.  Reporting included schedule status and progress, schedule look ahead, s-curve man-hour analysis of forecast versus actual, and mitigation plans to recover schedule delays. Prepared monthly invoices and weekly/monthly progress reports. Organized and controlled material procurement schedule to expedite material deliveries.

Planner/Scheduler, Rizzani De Eccher, Tajik Afghan Bridge, Delhi Metro Rail Project

START Date
END Date

Project Control Engineer reporting to the Branch Manager. Performed planning and scheduling, prepared schedule of works, and reports for client and consultant submission.  Reporting included schedule status and progress, schedule look ahead, s-curve man-hour analysis of forecast versus actual, and mitigation plans to recover schedule delays. Prepared monthly invoices and weekly/monthly progress reports. Organized and controlled material procurement schedule to expedite material deliveries.

Planner/Scheduler, Rizzani De Eccher, Tajik Afghan Bridge, Delhi Metro Rail Project

START Date
END Date

Project Control Engineer reporting to the Branch Manager. Performed planning and scheduling, prepared schedule of works, and reports for client and consultant submission.  Reporting included schedule status and progress, schedule look ahead, s-curve man-hour analysis of forecast versus actual, and mitigation plans to recover schedule delays. Prepared monthly invoices and weekly/monthly progress reports. Organized and controlled material procurement schedule to expedite material deliveries.

Project Control Manager, Rizzani De Eccher, Tajikistan, Azerbaijan, Kazakhstan, Russia-Moscow, Algeri, RAK UAE heavy building, luxury hotels, railways projects

START Date
END Date

Tajikistan, Azerbaijan, Kazakhstan, Russia-Moscow, Algeri, RAK UAE heavy building, luxury hotels, railways projects

Rizzani De Eccher Project Controls Manager

Director of Planning and Cost Management for Rizzani Group and Assistant to Operation Manager Moscow branch

Moscow Branch restructuring plan

Introduce planning and cost controlling methodologies

Improve company project management

Coordinate worldwide planning and cost group

Business planning/ company result by branch/ line of business

Project Auditing activities

Claim management support

Project financing support

Engineering and main contractor vendor research and qualification