Reliance Industries Limited, India

Reliance Industries Limited, India

Ravi Kiran Vedula

First Name
Ravi Kiran
Last Name
Vedula
Professional Since
Oldest experience
Years Experience
17
Telephone Number
919998983358

Worked as a team member in commissioning team of Coker unit of new refinery in RIL.

Computed standard minimum times for various maintenance activities.

Developed Schedule Deviation Cause master for various units of refinery.

Improved PM compliance of refinery complex to 95%.

Improved availability and utilization of resources by developing a central pool of resources for whole refinery

Prepared Bill of materials for all equipments for better identification of spares and spare management.

EPC Senior Planner, "Reliance Industries Limited, India", refinery

START Date
END Date

v  Preparing EPCO schedules with inputs from engineering and procurement departments/EP contractors in Primavera P6 & MS Project 2010.

v  Resource loading & levelling.

v  Analyzing the progress using S-Curve. Generating reports on daily, weekly & fortnightly basis depicting the Achievements, Critical Issues, Schedule Analysis, Progress Analysis, Front Analysis, Equipment Analysis and Manpower Analysis.

GOPIKRISHNA SAHUKAR

First Name
GOPIKRISHNA
Last Name
SAHUKAR
Professional Since
Oldest experience
Years Experience
23
Telephone Number
+919989094205
LinkedIn Profile
S.Gopikrishna
Facebook Profile
S.Gopikrishna
Twitter Profile
S.Gopikrishna

 Profile

Project Planning Engineer, Petro Energy Contracting, "Reliance Industries Limited, India",Jindal Saw Ltd., OIL & GAS ,Pipeline & Refinary,Petro Chemical projects

START Date
END Date

 

v  Developing Level I, II, III Schedule in Primavera & MS Projects.

v  Working experience of over 35,000 activities on planning software.

v  Calculating Resource requirements like manpower and Plant & Machinery requirements for the project.

v  Liquidating the Project quantitatively across the duration as per schedule.

Reliance Industries Limited, India Project Engineer

Worked as a project engineer in commissioning and start up team of new refinery. Took active part in document review, preparation of quality action plans for erection and commissioning of equipment, hydro test of all exchangers, mechanical checks of piping, steam blowing, spare codification, association to equipment,assessment, quality checks upon receipt.

Reliance Industries Limited, India Project Controls Manager

Cross-country Gas Pipeline Projects–

Worked on East West Gas Pipeline (EWPL) project having 1369 km (48” diameter) trunk line, 572 km Spur lines, 10 Compressor Stations, 38 Mainline Valves, 1414 crossings out of which 11 crossings by HDD/ Micro-tunneling.

Responsibilities:

o     Involved in scheduling, monitoring and reporting of Engineering, Procurement and Construction activities of Compressor Stations and Metering and Regulating Stations of East West Gas Pipeline Project.

Lead Project Control Engineer, "Reliance Industries Limited, India", EPC of New Onshore Gas Plant upstream & Compression Facilities

START Date

Current Role

Working as Lead Engineer (Project Controls) and involved in Project Control activities of KGD6 – 80MMCMD Onshore Gas Terminal Project (Green field) at Kakinada (AP) commencing from Dredging works, Site Grading, Piling Works, Construction Jetty and Infrastructure facilities establishment till Commissioning of Onshore Terminal Project including Infrastructure Buildings 

Responsibilities:

  • Interface with Construction manager, Project Control Manager and Discipline leads
  • Preparation of WBS, Construction Schedules and Pro