Project Engineer, Parsons Brinckerhoff, NA
Sabbatical to go travelling - In contract with Parsons Brinckerhoff
Parsons Brinckerhoff
Sabbatical to go travelling - In contract with Parsons Brinckerhoff
Construction Manager – Chiswell Street Hotel (December 2007 – September 2008):
This was a £25m project with a construction management procurement process, involving the refurbishment of a 250 year Grade 2 listed old brewery building into a 215 bedroom hotel with spa, meeting rooms, bars, and other facilities. Involvement included the following: management of the site setup, multi-service gang, the internal fabric repair and dry-lining trade contractors.
Project Engineer – King’s Cross and Mile End Underground Station Modernisations (October 2008 – October 2009):
These projects were in the value of £31m and £32m, under a construction management procurement method.
Construction Planning – Thameslink KO2 London Bridge & Bermondsey Dive Under GRIP 3 & 4, Network Rail (October 2010 - July 2011):
Construction Planning & Optioneering Consultancy for the delivery and construction of London Bridge Station and Bermondsey Station (Key Output 2) as part of the Thameslink Project. Assisting Network Rail in developing a robust work breakdown structure, delivery programme, engineering, construction strategy for various options for the redevelopment of the stations, as part of the Grip 3 & 4 process.
Construction Planning & 3D/4D Modelling – Heathrow Terminal 2B (August 2011 – Present):
Planner on the £460m second phase of a satellite building to support Heathrow Terminal 2. Assisting in the overall T2B 4D modelling duties for the substructure and superstructure works.
Project: T2B (London Heathrow Terminal 2)
My position has covered a wide range of areas from producing a Detailed Programme covering Design, Procurement, Manufacture and Assembly for all works disciplines. Also update the programme, attend all the technical, co-ordination and progress update meetings.
I developed programme in close contact with the engineers and project managers. In addition I work with the projects controls team and extract cost information from the programme for EV and other analysis.
Project Planner working on mostly mechanical projects in the mining, water and power industries. Main planning software is Primavera 6.7 with occational MSP. Planning projects from feasability to commissioning and close-out. Came through the ranks starting as an apprentice boilermaker. Loving the planning scene and always keen to learn more. Also PMP and PMI-SP.
Senior planner for Parsons Brinkerhoff working on various mining projects.