Jurong Shipyard Pte Ltd

Structural and Coating Lead, Jurong Shipyard Pte Ltd, Modec OSX3

J
Jude Lee 👤 Member for 8 years 5 months
START Date
END Date

Executed the construction portion of project plans through micro planning and ensured that siteprogress is aligned with project’s overall schedule. Led a team of multi-discipline supervisors to monitorand provide guidance to sub-contractors on day-to-day direction of site activities. Ensured smooth andsafe execution of site work.

Structural and Piping Lead, Jurong Shipyard Pte Ltd, Petrofras P62

J
Jude Lee 👤 Member for 8 years 5 months
START Date
END Date

Executed the construction portion of project plans through micro planning and ensured that siteprogress is aligned with project’s overall schedule. Led a team of multi-discipline supervisors to monitorand provide guidance to sub-contractors on day-to-day direction of site activities. Ensured smooth andsafe execution of site work.

Piping and Mechanical Lead, Jurong Shipyard Pte Ltd, Noble Jim Day

J
Jude Lee 👤 Member for 8 years 5 months
START Date
END Date

Executed the construction portion of project plans through micro planning and ensured that siteprogress is aligned with project’s overall schedule. Led a team of multi-discipline supervisors to monitorand provide guidance to sub-contractors on day-to-day direction of site activities. Ensured smooth andsafe execution of site work.

PLANNING ENGINEER, Jurong Shipyard Pte Ltd, Maersk Convincer; Petrojack IV; Atwood Osprey; Seadrill West Elara

START Date
END Date
Experience Hours (Planning & Scheduling)
5000
Experience Hours (Cost Management)
250

Schedule Setup

Setup Schedule based on Contract WBS in line with company planning policies and guidelines.

Usage of Manpower / KPIs to determine durations of activities and to plan for construction sequencing.

Setup of physical progress measurement using key measurables (Steel Tonnage / Pipe Spools / Cable Length / Termination points etc)

 

Schedule Analysis and Control / Problem Solving

Conduct weekly analysis of schedule (Float, Critical Path, Manpower, Resource)