Impregilo

Impregilo

Project Control Manager, Impregilo, Italy - MOSE -Venice Lagoon

START Date
END Date
Experience Hours (Planning & Scheduling)
1000
Experience Hours (Cost Management)
1000

Project Control Manager

project: Mo.Se, Mobile Dams System Venice Lagoon, CVN Consorzio Venezia Nuova (italy)

 

General Contractor design and build for the MoSe (mobile dams) in Venice lagoon.

- Implementing and running Planning and Cost Control project methodologies.

- Organizing and running Project Control Office and Project IT Services department

Project Control Manager, Impregilo, Italy - Motorway Passante di Mestre

START Date
END Date
Experience Hours (Planning & Scheduling)
1000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
500

Project Control Manager

project: Passante di Mestre S.C.p.A. ANAS

 

General Contractor design and build 33km motorway, 840M€.

 

- Analyzing, defining and implementing planning and cost control methodologies.

- Organizing and running Project Management Office and Project IT Services department.

- Defining and maintaining project data structures: EPS, PBS, WBS, OBS, CAPs.

- Monthly progress construction reports submitted to the Client.

Assistant Manager Extension of Time (EOT) Section, Impregilo, Ghazi Barotha Hydropower Project

START Date
END Date
Experience Hours (Forensic Analysis)
14000

Impregilo, a major Italian construction company specializing in the construction of complex infrastructure projects, led the joint venture for the construction of 1450 megawatt Ghazi Barotha Hydropower Project involving construction of 53 km Power Channel and Barrage.

 

Job Profile & Major Achievements:

Ant Pir

A
Ant Pir 👤 Member for 12 years 11 months
First Name
Ant
Last Name
Pir
Professional Since
Oldest experience
Years Experience
7

Current Competencies:

Planning Engineer, Impregilo, Ingula pumped Storage Scheme (South Africa)

A
Ant Pir 👤 Member for 12 years 11 months
START Date
END Date

Duties:

  • Updated status schedule and develop detailed schedule and recovery schedule in P6.
  • Monitored all phases of the program, including engineering, procurement, construction and start-up of facilities with PRIMAVERA P6 (Including Mechanical, Electrical, Civil and structural, Piping, Instrumentation, Procurement, so on ).
  • Provided accurate and appropriate project reporting with PRIMAVERA P6 and MS OFFICE for managers periodic as a progress report and regularly attend scheduling meetings to assess progress.