Anil Potnuru
Extensive experience of more than 20 plus years in construction field in different areas like Planning using Primavera P6 latest version 18.8, Claims Preparation / Reviewing, Contracts Management, Change Order Management, Site Monitoring / Execution & QS etc.
Planning Manager, GHANTOOT GROUP, Mix use development - Roads and Infrastructure project
- Complete and generate the Planning Package, in close coordination with executing parties and Project Management Team
- Provides overall management of division-related planning issues
- Evaluates operations and activities of assigned responsibilities
- Methods and techniques of effective technical report preparation and presentation
- Train all subordinates of all planning team in various system
Fritz Mendoza
Ten (10) Years of highly well experienced in the field of civil construction, Soil improvements such as stone columns & pilings, construction of high rise buildings, warehouses, public establishments & offices, villas, material take-off, scheduling, contracts management and with broad knowledge and technique on cost control & project control, cost coding, earn value, value engineering, risk management, procurement management, claims & variations management, quantity surveying,NRM-1,NRM-2,NRM-3,POMI,SMM7,CESMM-3, client interim payment applications, EOT(Extension of Time) app
Project Cost Control Engineer, GHANTOOT GROUP, Abu Dhabi Trade Center Extension Phase 3
Position: Senior QS/Cost Control Engineer
Company: Ghantoot Group General Contracting Building Division
Project Name: Abu Dhabi Trade Center Extension Phase 3
Location: Mena Road,Abu Dhabi, UAE
Start Date: May 2013
End Date: Up to Current Date
Duties & Responsibilities:
Preparing tender and contract documents, including bills of quantities with the project team.