Construction Interface planner, Fluor UK, TCO – FGP – WPMP (Wellhead Pressure Management Project)

START Date
END Date

This role is to coordinate and maintain the engineering Construction Interface
tracker which is the main multi discipline focal point document for the engineering
team in Farnborough, Almaty and Houston with the construction site in Tengiz,
Kazakhstan.
To maintain good communication between all WBS areas, existing area meetings were
enhansed with additional meetings so that the tracker was up to date and all changes visable for discussion in the weekly review meeting by management and lead engineers.

Any slippages within the multiple P6 schedules had to be challenged by liaising

Senior Technical Planning Engineer, Fluor UK, Tengiz Future Growth Project - Oil & Gas Kazakhstan / Simandou Iron Ore Project - Guinea Africa

START Date
END Date
Experience Hours (Planning & Scheduling)
1500
Experience Hours (Cost Management)
100

     Tengiz Future Growth Project - Oil & Gas Kazakhstan