Project Manager, Exterran, Oak Grove and CRPs

START Date
END Date

Responsible for earthwork and construction of the pad (7.1MM cubic yard of earthmovement) and delivery of first 200MMSCFD equipment and balance of plant engineering. Scope managed was Engineering, Procurement, and Construction Management of three trains of 200MMSCFD Cryogenic trains with balance of plant, with planned built-out capacity of 2BSCFD. Key achievement was selection of EPC subcontractors for scope that was not self-performed.

Project Engineer, Exterran, Khor Mor LPG Recovery Plant and Early Production Facility

START Date
END Date

Delivered a profitable margin on technical construction and commissioning support at site of two identical 150MMSCFD Cyrogenic trains and engineering, procurement and fabrication of EPF plant skids including balance of plant, by leading coordination with client's team in UAE and Iraq, internal engineering team in US and AE, and Construction and Commissioning Manager at site.

Project Engineer and later promoted as Project Manager, Exterran, Majnoon Early Production System

START Date
END Date

Flawless Project Delivery on the scope of Engineering, Procurement, and Fabrication for skid mounted packages and modules for two identical 50KBOPD trains,with common facilities, and utilities to form Well pad and part of Central Processing Facilities.

EMMANUEL OFOH

First Name
EMMANUEL
Last Name
OFOH
Oldest experience
Years Experience
41
Telephone Number
+2348030600064; +2348052365566

Experienced Electrical and Instrumentation Engineer possessing a broad technical background in Electrical, Instrumentation, Control, Electronics, Automation,Project Engineering and Project Management in the Oil & Gas, manufacturing and service industries.



I have over seven (7) years hands-on technical/engineering experience in Oil and Gas process plants and manufacturing plants Instrumentation, Production Operations/Maintenance.

Lead Electrical and Instrumentation/Control, Exterran, Gbaran-Ubie EPF (GAS Processing Facility)

START Date

• System Integration for Plants, Equipment and Machines DCS/PLC/SCADA/HMI/F&G.



• E&I Systems Design and Implementation



• Installation, Testing, Commissioning and Maintenance of Electrical and Instrumentation systems for Process plants, Compressors, Turbines, Motors, and Generators.



• E&I devices/system Testing, Inspection and QAQC.



• Project Engineering and Project Management



• Production Operations



• Radiation Safety/HSE

Exterran Planner

R
Rey Relato 👤 Member for 18 years 8 months

     Establish the overall baseline schedule in P6 with client approval for base lining.

     Update and maintain the schedule. Generate weekly forecast schedule update report and three week look-ahead construction schedule.

     Prepare weekly schedule analysis report and progress reports with S-Curves for engineering, procurement, construction and commissioning.