EPC Consultants

EPC Consultants

Cost and Schedule Controls Manager/Scheduler/Coordinator, EPC Consultants, VTA/BART (SVBX) / Berryessa Extension Project $2.5 Billion- San Jose

START Date
END Date
Experience Hours (Planning & Scheduling)
1300
Experience Hours (Cost Management)
100
Experience Hours (Forensic Analysis)
600

 

EPC Consultants, Inc., San Francisco, CA                                          (2013 – 2015)

 

VTA/BART (SVBX) / Berryessa Extension Project - San Jose:

Scheduler/ Cost Controls Engineer, EPC Consultants, Inc. San Francisco, CA for Bureau of Environmental Services , Willamette River Combined Sewer Overflows CSO Tunnel Program.

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
300

1- The East Side CSO ESCSO Tunnel, Portland, OR, $450 million, 2005-2011
The projects used Cost-Reimbursable-Fixed-Fee. This alternate contract method successfully eliminated all claims and disputes for both projects. The entire program was completed on-time and under-budget with no outstanding contractual issues and no claims.