      My name is Walter Fremer and I am the senior scheduler at Durr Mechanical, Inc.

Scheduler, Durr Mechanical Inc., Croton Water Filtration Plant- NYC DEP

START Date
Experience Hours (Planning & Scheduling)
1800
Experience Hours (Forensic Analysis)
200

HVAC Prime Scheduler,

Preparation of Resource loaded Level 3 P3 schedule

Perform Monthly Updates.

Incorporate Change Order Fragnets into Project Schedule.

Assist in preparation of Extension of Time Requests.

Assist in preparation of monthly Notifications of Delay.

 

Project Scheduler / Project Controls, Durr Mechanical Inc., Towantic Energy Center

START Date
Experience Hours (Planning & Scheduling)
900
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
100

Project Scheduler / Project Controls

Preparation of resource loaded Level 3 P6 schedule.

Provide weekly Three Week Look-Ahead Schedule ( in Excel ).

Update project schedule bi-weekly.

Develop monthly performance curves.

Incorporate change order fragnets into project schedule.

Prepare recovery schedules as needed.

Project Scheduler, Durr Mechanical Inc., Covanta

START Date
END Date
Experience Hours (Planning & Scheduling)
1400
Experience Hours (Forensic Analysis)
50

Scheduler

Joined project in progress.

Responsible for revisions to on-going schedule.

Preparation of recovery schedules.

Updated schedule weekly and distribute to Project Team.

Incorporated change order fragnets as required.