Degremont

Degremont

Tamer Medhat

First Name
Tamer
Last Name
Medhat
Years Experience
0
Telephone Number
+2 01223927080

Planning Engineer

working with Microsoft Project P3, P5, P6

My profile is a production Engineer, i had join a multinational company working in EPC projects since 8 years

Planning engineer, DEGREMONT, 3 sewage water plants

START Date
END Date

 

Construction of the time schedule for three sewage treatment plants:

 

  • Planning & scheduling of the engineering, procurement and construction phases;
  • Methods and procedures to measure the progress;
  • Weekly and monthly reports;
  • Training of an engineer for the mission.

Cyril GALZIN

First Name
Cyril
Last Name
GALZIN
Professional Since
Years Experience
0

15 years of experience in Planning & Construction coordination. Water Treatment, Oil & Gaz & Civil Works.

Alin Mathews

First Name
Alin
Last Name
Mathews
Professional Since
Oldest experience
Years Experience
41
Telephone Number
0097455065165 or 0097466716267

 

1)      Well Versed In Primavera P6, P3 & Microsoft Project Software. Expert in Analyzing Critical Path & Reviewing and Answering for the Critical Path Submitting by Contractors for the Claims.

2)      Preparing Progress Curves and Histograms, Look Ahead Programs, Efficiency Reports& Monthly Reports for Client

Degremont Planner

As a planner working on water and wastewater projects my role was to provide programmes from design to commissioning and to monitor and report against them. Also, the role consisted of producing early warnings to comply with the NEC contract conditions.

Senior Project Controls Engineer, Degremont, DOHA WEST sewage treatment works extension No.3

A
Amin Sorour 👤 Member for 20 years 4 months
START Date
END Date

The design-build contract for Doha West is worth USD 180 million and the plant operation contract totals USD 80 million, for a total amount of USD 260 million, awarded by the Public Works Authority in 2006.This is a 135,000 m3/day wastewater facility, the first in the Middle East to use tertiary treatment with ultra filtration membranes. All the treated water will be used for farm irrigation after the commissioning late 2008.

Degremont Project Controls Manager

B
Bruno ABBEY 👤 Member for 16 years 11 months

VALENTON WASTE WATER TREATMENT PLANT

•     Coordination of the pipe working on the new purification station site.

•     Supervision and management, of 3 foremen and 55 peoples including their mobilization and demobilization;

•     Follow up of the materials order and delivery;

•     Interface with the Client;

•     Follow trough of the planning and reporting to the Company.