BNFL (Sellafield Sites)

Bid/Project Planning Engineer, BNFL (Sellafield Sites), Nuclear

START Date
END Date
  • Planning Engineer Roles and Responsibilities 2010/2013
  • Working on Major Projects within the Business
  • Using Primavera to carrying out the Planning applications required for the Project:
  • Develop the Project Programme
  • Develop the Work Breakdown Structure with Resources and Cost ]
  • Monitor, Control and report on project progress
  • DV Cleared

Work Week Manager Roles and Resposibilities 2005/2010

Planning Engineer, BNFL (Sellafield Sites), THORP Nuclear Plant

START Date
END Date

Responsible for the control and monitoring of several contractors programmes and for integrating them into an overall construction programme.

Development of a Sub Station cabling and commissioning programme to provide phased electrical start up to meet the overall THORP plant commissioning programme.

Software used was Artemis 2000 and SMART integrated package for general reporting.

Project Manager, BNFL (Sellafield Sites), B38 (Sellafield) Retrievals

START Date
END Date

The B38 project’s aim is to safely retrieve radioactive waste from an old building whilst mitigating explosion risk during retrievals due to the decomposition of magnox swarf producing hydrogen.

Employed as a Project Manager for 4 projects (total value £2M P/A) under the B38 Retrievals portfolio including bi-monthly progress reporting to Senior Management for the whole of the portfolio (value £20M P/A).