Birse Metro

Birse Metro

Planning Manager, Birse Metro, Various

START Date
END Date
Experience Hours (Planning & Scheduling)
5000
Experience Hours (Cost Management)
2000
Experience Hours (Forensic Analysis)
3000

Nov.4 – Feb.6 Project: Underfloor Wheel Lathe, Northfields Depot (£2.8M)This project is the design and construction of a facility (20m x 15m x 7m high) and installation of the underfloor wheel lathe at Northfields Depot.

Senior Tender Planner, Birse Metro, TFL Station Refurbishments

START Date
END Date
Experience Hours (Planning & Scheduling)
300
Experience Hours (Cost Management)
100
Experience Hours (Forensic Analysis)
100

Jul.9 – Aug.9        Tender:     Hammersmith Station Platform Extensions                  (£4M)

Planner, Birse Metro, Step Free Access

M
Mark Wright 👤 Member for 17 years 6 months
START Date
END Date

Birse Metro Step Free Access (Bank of four) London Underground December 2008 to June 2009 (Planning software P6)

Working to provide Step Free Access to four London Underground sites (Greenford, West Kensington, Newbury Park, Amersham) (Planning software P6)

Initially working on two programmes covering installation of Lifts stairs and bridge at Amersham & Newbury Park

Working under an NEC contract to London Underground.

Birse Metro Senior Planner

•     NEC Contract and subcontractor resource management.

•     Develop multi-discipline (Premises, Mechanical, Electrical, and Communications) programme based on RIBA design / Scope Documentation.

•     Ensure programmes meet NEC3 Engineering and Construction Contract specifications.

•     Site based progress management.

•     Work package costing, resourcing, schedule implementation and analysis.