site engineer, Besix Orascom JV, Grand Egyptian mesum
checking formwork
checking formwork
Ø Issue the tender schedule of the project; assign major resources histogram using Bill of Quantity in coordination with Quantity Surveying and tender departments.
Ø Preparation of the project cash flow to be submitted to tender department.
Ø Prepare Schedule Narrative to assist tender department in preparing the method of statement for the project in tender stage.
1) Orascom Construction OCI- BESIX
Since Feb 2009 (Current Employment)
Senior Planning & Scheduling Engineer
A. Giza North 1500MW Combined Cycle, Power Plant, Contract Value $ 70.2 Million + EGP 562.7 Million.
Ø Issue the tender schedule of the project; assign major resources histogram using Bill of Quantity in coordination with Quantity Surveying and tender departments.