Balfour Beatty Construction Services UK

Project control & Planning Manager, Balfour Beatty Construction Services UK, UK RAF Marham Lightning FII Freedom of Action Facilities

START Date
END Date

To assist 3 days a week with a small taskforce in assessing the current on-site
construction schedule and work sequence with the principle contractor to mitigate
delays and the avoidance of LD’s in meeting the client’s deadlines for the
construction and fit out of maintenance and training facilities for the new F35
aircraft.
Further development of a ASTA Power Project resourced completion schedule using earlyaccess information supplied by the client to meet their critical contractual fit out requirements.

Senior M&P Planner, Balfour Beatty Construction Services UK, TMF Project - Urenco Capenhurst

START Date
END Date

This is Balfour Beatty Major Constructions first integrated project combining their Electrical division and their Mechanical Bromborough office. Additional to the development of the M&P scope with the integration of the E&I scope was the alignment of supervision to the benefits of timely and accurate reporting allowing them to arrange their resources more efficiently.
Due to ongoing scheduling access issues with other contractors, engineering and material shortages the project was re-baselining twice.

Planner, Balfour Beatty Construction Services UK, University of Sussex

J
Jason Bayat 👤 Member for 8 years 8 months
START Date
Experience Hours (Planning & Scheduling)
50
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50

I am currently working at University of Sussex’s £120m East Slope project which is part of an investment programme to modernise and improve the University

Jason Bayat

J
Jason Bayat 👤 Member for 8 years 8 months
First Name
Jason
Last Name
Bayat
Professional Since
Oldest experience
Years Experience
5
Telephone Number
07930850865
LinkedIn Profile
in/jason-bayat-19b9a48b/

• Ensuring that the Contract Programme is produced, managed and maintained in accordance with the planning procedures 

Planner, Balfour Beatty Construction Services UK, Ethane Import Terminal Project

START Date

I am a Project planner currently working on the construction of Propane Storage tank and tank base for Ethane Import Terminal. 

Duties;

Monthly programme uppdates 

Weekly progress schedule

3 Weekly programme

Monthly report

Gulam Kassam

First Name
Gulam
Last Name
Kassam
Professional Since
Years Experience
0
Telephone Number
07921 184319
LinkedIn Profile
https://www.linkedin.com/in/gulamkassam?trk=hp-identity-photo

Planning and Project Controls Manager

Primavera P6

Performance Management: Milestone Tracking, EVM, Entitlement & Claims

TILOS and Eidolon

Programme Management

Primavera Risk Analysis

Forensic Planning and Claims

Shedule Analysis (Acumen)

Training at all levels (from graduates to Planning Managers)

Lead/Senior Planning Engineer, Balfour Beatty Construction Services UK, London Underground Stations Upgrade Projects

START Date
END Date
Experience Hours (Planning & Scheduling)
1500
Experience Hours (Cost Management)
1500
Experience Hours (Forensic Analysis)
1500

Programme Involvement

Metronet PPP (£2 Billion)

Keith Harris

First Name
Keith
Last Name
Harris
Professional Since
Years Experience
0

20 years mainly working on Claims work on commercial projects in SE.

Includes site Project Planning & reporting, short term programmes and lookaheads.

Last 2 years working with large UK contractor on tender bids on projects £50 - 140m

Have used P6 but have ASTA PP all my career