ARCHIRODON CONSTRUCTION (OVERSEAS)

Planning & Project Controls Engineer, ARCHIRODON CONSTRUCTION (OVERSEAS), BAB 485 MBD Sustainable Facilities Project

Z
Zain Hanif 👤 Member for 5 years 1 month
START Date

Establishment of progress measurement systems

Creation of project schedules

Risk analysis

Negotiation and award of procurement packages

Project management

Planning & Project Controls Engineer, ARCHIRODON CONSTRUCTION (OVERSEAS), BAB 485 MBD Sustainable Facilities Project

Z
Zain Hanif 👤 Member for 5 years 1 month
START Date

Establishment of progress measurement systems

Creation of project schedules

Risk analysis

Negotiation and award of procurement packages

Project management

Project Controls Engineer , ARCHIRODON CONSTRUCTION (OVERSEAS), Tripoli Harbour Breakwater

START Date
END Date
Experience Hours (Planning & Scheduling)
600
Experience Hours (Cost Management)
2000
  • Updating of Project Time Schedule
  • Monitor Progress periodically and Compare it with base line and provide solutions.
  • Implement the work schedule and monitor progress of the work for timely execution of the project through daily/weekly/monthly/ reports with respect to review of the overall project
  • planning report such as preparation of manpower requirements for the project, preparation of material procurement reports.
  • , productivities, important events, verbal site instructions, etc.
  • Preparation of monthly client invoices
  • Participates in p

Project Controls Engineer , ARCHIRODON CONSTRUCTION (OVERSEAS), Tripoli Harbour Breakwater

START Date
END Date
Experience Hours (Planning & Scheduling)
600
Experience Hours (Cost Management)
2000
  • Updating of Project Time Schedule
  • Monitor Progress periodically and Compare it with base line and provide solutions.
  • Implement the work schedule and monitor progress of the work for timely execution of the project through daily/weekly/monthly/ reports with respect to review of the overall project
  • planning report such as preparation of manpower requirements for the project, preparation of material procurement reports.
  • , productivities, important events, verbal site instructions, etc.
  • Preparation of monthly client invoices
  • Participates in p

Project Controls Engineer , ARCHIRODON CONSTRUCTION (OVERSEAS), Tripoli Harbour Breakwater

START Date
END Date
Experience Hours (Planning & Scheduling)
600
Experience Hours (Cost Management)
2000
  • Updating of Project Time Schedule
  • Monitor Progress periodically and Compare it with base line and provide solutions.
  • Implement the work schedule and monitor progress of the work for timely execution of the project through daily/weekly/monthly/ reports with respect to review of the overall project
  • planning report such as preparation of manpower requirements for the project, preparation of material procurement reports.
  • , productivities, important events, verbal site instructions, etc.
  • Preparation of monthly client invoices
  • Participates in p

Project Controls Engineer , ARCHIRODON CONSTRUCTION (OVERSEAS), Tripoli Harbour Breakwater

START Date
END Date
Experience Hours (Planning & Scheduling)
600
Experience Hours (Cost Management)
2000
  • Updating of Project Time Schedule
  • Monitor Progress periodically and Compare it with base line and provide solutions.
  • Implement the work schedule and monitor progress of the work for timely execution of the project through daily/weekly/monthly/ reports with respect to review of the overall project
  • planning report such as preparation of manpower requirements for the project, preparation of material procurement reports.
  • , productivities, important events, verbal site instructions, etc.
  • Preparation of monthly client invoices
  • Participates in p

Planning & Project Control Engineer, ARCHIRODON CONSTRUCTION (OVERSEAS), & Power infrastructure works and 132kv/66kv substation distibution station

A
Assem Osman 👤 Member for 9 years 11 months
START Date
END Date
Experience Hours (Planning & Scheduling)
1500
Experience Hours (Cost Management)
300
Experience Hours (Forensic Analysis)
100

 • Developed comprehensive baseline CPM schedule.

• Responsible for opening, updating and closing cost centers of the project.

• Allocated the resources for activities and calculate productivity of projects.

• Updated schedules and analyzed manpower and cost allocations.

• Cost Estimation.

• Maintained a report of actual cost against estimated budget for all current projects at the site operations and submitted it monthly.

• Forecasted the estimate at completion to anticipate the cost trend of the project.

Jeelani amin

First Name
Jeelani
Last Name
amin
Professional Since
Years Experience
0
Telephone Number
00966548680446

Excellent understanding of Material Control

Excellent Knowledge of Quantity estimation.

Excellent Knowledge of Project Execution.

  Excellent Knowledge of Project Management Tools.