Project Planner, AMEC, London Underground Power Upgrades

E
Eden Day 👤 Member for 15 years 8 months
START Date
END Date

Producing Conceptual Design Statement’s on upgrading the power to Metropolitan, Circle & District lines. Working out of Royal Mint Court, London. My role as Project Planner required me to co-ordinate team efforts when the manager was unavailable. My primary responsibilities were to monitor and update the schedule, make alterations where required, input expended man hours and compile Earned Value reports. I also attended daily review meetings with the project manager and CDS champions to ensure current progress reporting was accurate.

Forensic Claims Analysis Planner, AMEC, Kilroot FGD Claim

E
Eden Day 👤 Member for 15 years 8 months
START Date
END Date

As Forensic Claims Analysis Planner on the Kilroot FGD project, I was working with a team of ten core persons including legal advisors to produce a model with audit trails and other required evidentiary support to form a successful legal case.

Project Controller, AMEC, Longannet Power Station - FGD

E
Eden Day 👤 Member for 15 years 8 months
START Date
END Date

Managing the production of a Level 5 commissioning programme to be integrated into the master delivery programmes, working as Project Controller at the Longannet Power Station, Scotland. Constant communication with the Commissioning Manager as well as daily meetings with the project team allow me to be kept up to date of current progress and able drive the planning teams within the joint venture to implement the solution both accurately and correctly. I also frequently interface with the client in a formal setting.

Project Controller, AMEC, DOW De-Commissioning Project

E
Eden Day 👤 Member for 15 years 8 months
START Date
END Date

Working as Project Controller based at the DOW Chemicals EOEG Plant on the Wilton site, I managed the production of a fully resource loaded Level 5 Decommissioning programme with a value of £7million for Process Division. As part of this I am the first AMEC employee to successfully use the PICS database system and Primavera 6 together. This involved using the SDK to automate the integration between MS Access & P6.

Planning Engineer - Construction, AMEC, Milford COGEN on the DRAGON Project

A
Alan Smith 👤 Member for 15 years 7 months
START Date
END Date

Develop and detail the construction and commissioning schedule for the Milford COGEN facility, an offshoot of the DRGAON Project. Utilising DRAGON Project Boil Off Gas to drive co generation waste heat boilers and gas turbines in order to generate power sufficient to drive the Dragon Project whilst also exporting to the nation grid any surplus power.

PLANNING ENGINEER, QGC, AMEC, PLUS THREE CONSULTANTS, TURNER & TOWNSEND, SANTOS, GLNG, QCLNG,

START Date

Project Planning for Client and Contractor from FEED thru EPC construction including EOT (forensic claim planning).

Started with Infrastructure and Building industry for a collective 5 years and 10 years in Oil & Gas /Petro-Chem industry.

Planning Manager, AMEC, Sub Surface Lines Power Upgrade

START Date
END Date

Planning & Reporting Manager on Power Upgrade Project for Amec

 

  • Negotiated with client to create new SSL Scoping & Development programme to facilitate requirements of MPD, EV and period reporting.
  • Managed production of Design & Build programmes for client to use in ITT successfully recovering lost time in the delivery milestone.
  • Improved relationship between client & contractor.
  • Managed a team of ten planner