  • Project and Program Control Management:

#planning #engineer #D&B #planningengineer, al huda engineering works, Egyptian Liquefied Natural Gas (ELNG)

START Date
END Date
Experience Hours (Planning & Scheduling)
10000
Experience Hours (Cost Management)
9000
Experience Hours (Forensic Analysis)
8500
  • Planned, implemented and directed overall project schedules and controls to support the Project Director in managing project review, control and reporting processes and highlight abnormalities in project performance.
  • Devised and executed all aspects of planning and scheduling deliverables of the project including preparation of resource loaded schedules, tracking of actual against baselines, performing variance analysis and updating of weekly/monthly reports at the field and management levels.

#planning #engineer #D&B #planningengineer, al huda engineering works, Egyptian Liquefied Natural Gas (ELNG)

START Date
END Date
Experience Hours (Planning & Scheduling)
10000
Experience Hours (Cost Management)
9000
Experience Hours (Forensic Analysis)
8500
  • Planned, implemented and directed overall project schedules and controls to support the Project Director in managing project review, control and reporting processes and highlight abnormalities in project performance.
  • Devised and executed all aspects of planning and scheduling deliverables of the project including preparation of resource loaded schedules, tracking of actual against baselines, performing variance analysis and updating of weekly/monthly reports at the field and management levels.

#planning #engineer #D&B #planningengineer, al huda engineering works, Egyptian Liquefied Natural Gas (ELNG)

START Date
END Date
Experience Hours (Planning & Scheduling)
10000
Experience Hours (Cost Management)
9000
Experience Hours (Forensic Analysis)
8500
  • Planned, implemented and directed overall project schedules and controls to support the Project Director in managing project review, control and reporting processes and highlight abnormalities in project performance.
  • Devised and executed all aspects of planning and scheduling deliverables of the project including preparation of resource loaded schedules, tracking of actual against baselines, performing variance analysis and updating of weekly/monthly reports at the field and management levels.

Advisor Planning - Sr Planning Engineer, al huda engineering works, (2) 3B+G+14 Stories+ Swimming Pool (Office %26 Residential) Building+Villas, 10 km of highway, 1100 MW Power Plant Project, CPC Pump station expansion project

START Date
Experience Hours (Planning & Scheduling)
8000
Experience Hours (Cost Management)
6000
Experience Hours (Forensic Analysis)
5000
  • Prepare Claims (EOT) Claims, prolongation Cost Claim & Disruption Claim
  • Prepare Project Planning Dossier including Project Control Procedure, Project Baseline Schedule, Deliverable Register, S Curve and Histogram& delay analysis
  • Developing detailed daily, weekly, and monthly project progress reports and submit to client
  • Creating executive summary and dashboard reports including key performance indicators (KPIs)&Delay Analysis which focus on status and issues of each project to allow project stakeholders to make timely decisions to resolve such issues

Advisor Planning - Sr Planning Engineer, al huda engineering works, (2) 3B+G+14 Stories+ Swimming Pool (Office %26 Residential) Building+Villas, 10 km of highway, 1100 MW Power Plant Project, CPC Pump station expansion project

START Date
Experience Hours (Planning & Scheduling)
8000
Experience Hours (Cost Management)
6000
Experience Hours (Forensic Analysis)
5000
  • Prepare Claims (EOT) Claims, prolongation Cost Claim & Disruption Claim
  • Prepare Project Planning Dossier including Project Control Procedure, Project Baseline Schedule, Deliverable Register, S Curve and Histogram& delay analysis
  • Developing detailed daily, weekly, and monthly project progress reports and submit to client
  • Creating executive summary and dashboard reports including key performance indicators (KPIs)&Delay Analysis which focus on status and issues of each project to allow project stakeholders to make timely decisions to resolve such issues

4D Planning Consultant update base line schedule review, / Construction Project Planner / Senior Planner / Forensic Analyst, AL HUDA Engineering Works, (2) 3B+G+14 Stories+ Swimming Pool (Office %26 Residential) Building+Villas, 10 km of highway, 1100 MW

START Date
Experience Hours (Planning & Scheduling)
10000
Experience Hours (Cost Management)
10000
Experience Hours (Forensic Analysis)
6500
  • Prepare Claims (EOT) Claims, prolongation Cost Claim & Disruption Claim
  • Prepare Project Planning Dossier including Project Control Procedure, Project Baseline Schedule, Deliverable Register, S Curve and Histogram& delay analysis
  • Developing detailed daily, weekly, and monthly project progress reports and submit to client
  • Creating executive summary and dashboard reports including key performance indicators (KPIs)&Delay Analysis which focus on status and issues of each project to allow project stakeholders to make timely decisions to resolve such issues