1) Carillion plc

Project Planner Primavera P6, 1) Carillion plc, Great Eastern Overhead Line Renewals

START Date
END Date

Carillion Plc. (April 12 – Aug 2012)
Project Planner
Identifying capturing key deliverable dates start/finish is reflected on the programme.
Identify resources available
Agreeing the format of delivery testing and commission date with Project Manager
Evaluating problem areas and highlight areas of concern
Analysing information supplied by suppliers/sub-contractors.
Accumulating data from all parties and the project team.
Checking on progress & Verifying works complete & review any possible delays ensuring is been highlighted to the Sponsor.

Principal Planning Engineer, 1) Carillion plc, Kirkintilloch Link Road

A
Alan Holt 👤 Member for 21 years 9 months
START Date
END Date

I was the site Planning Engineer for the Kirkintilloch Link Road, a 4.6Km road valued at £35M reporting directly to the Contracts manager and Commerclai Manager.  I developed a fully logic linked cost and resource loaded programme as required by the NEC Contract Conditions for the works which was used both by Carillion and our various client groups for cost and value monitoring and forecasting and has become essential for Cost Index analysis.  The programme is also used to demonstrate the effect of compensation events and project manager’s instructions.