Mar 2009 to date Current Job Title : Scheduling Manager
Employer : SEPCOIII(Shandong Electric Power Company III)
City & Country : Damman, KSA
RAS Al KHAIRPOWER AND DESALINATION PLANT-PHASE 1
Near Dammam, Kingdom of Saudi Arabia,
Open Cycle and Combine cycle 3041MW
Contractor:ASC .JV (ACC and SEPCOIII).
EPC Contractor with all Engineering, Procurements, Construction and Testing & Commissioning of Plant till its Handing Over
My Job Responsibilities here includes:
- EPC Milestone Schedule Preparing and Monitoring
- EPC L1,L2,L3 schedule preparing, resource loading and monitoring
- Schedule preparing for the subcontractor, major equipment delivery
- Loading the Contract Price Activity wise in the Schedule.
- Preparation and Generation of Progress Curves of the EPC Project and Devising the Method of progress Measurement as per Client Requirement.
- Productivity Analysis Report Preparation per System to see the Efficiency of the Project Area and Zone wise.
- Critical Path analysis for the overall EPC Project. Marking the Long leading Activities and suggesting the Corrective actions.
- Analysis of Subcontractor’s/vendor’s weekly and Monthly Reports. Giving our subcontractors/vendorstargets for construction on weekly and Monthly basis.
- Supervising Equipment deployment and Material Procurement Plan development by Planning Engineers.
- Preparation of Monthly Presentation/reportfor Client.
- Progress update for Monthly invoice and also identification of Extra works other then Contractual Scope.
- Preparation of Monthly Progress for the Client.
- Preparation and maintaining the Budget in coordination with Cost Control Officers.
- Progress Verification for Engineering, Procurement & Construction with Client.
- Answering Contractual letters written by Client, Our Consortium partner ACCand Sub-Contractors.
- Conducting meeting with Our Site Construction Teams, Sub Contractors & Client to increase the productivityand resolve the issues.
- Preparing the Top Most critical items for the Project & Reporting them to the company top management.
May 2008to Oct 2009 Job Title : Sr. Planning Engineer
Employer : SEPCOIII (Shandong Electric Power Company III)
Country : Jordan
EPC contract for a combine cycle of the 2 gas turbines
1*108MW
Scope of work contains site works for Civil works, Mechanical works, Electrical works, I&C works etc
My Job Responsibilities here includes:
- Preparation and approval of Level 4 baseline & Latest Forecast Plan (on Primavera Project planner).
- Preparation of man power mobilization plan for direct & in direct employees.
- Preparation of equipment mobilization plan.
- Preparation of material requirement plan.
- Preparation of internal budget for the project.
- Preparation of weekly and monthly progress Report for Client. The reports contains Updated Level 4 plan on Primavera, Actual Progress Report as per site conditions.
- Productivity and efficiency calculations on FWBS (Field work Break down structure) Basis.
- Progress S curves preparing
March2007to October2008 Job Title : PlanningEngineer
Employer : SEPCOIII(Shandong Electric Power Company III)
Country : India
Project : Malula project coal power plant 1*108MW EPC contract
Monthly report to the client preparing
Malula project coal power plant 1*108MW EPC contract
SEPCOIII
Scope of work contains site works for Civil works, Mechanical works, Electrical works, I&C works etc
My Job Responsibilities here includes:
- Preparing and monitoring the milestone schedule for the whole site works
- Preparing the L4 schedule for site works together with each discipline
- Preparation of daily, weekly and monthly reports for the client.
- Weekly meeting, monthly meeting preparing for internal and subcontractors
- Critical path analysis for the whole project
- Monitoring the engineering and material delivery schedule match with the site works
August2005to March2007Job Title : Civil engineer/Planning Engineer
Employer : SEPCOIII(Shandong Electric Power Company III)
Country : China
Project : Qinzhou Guangxi Coal PowerPlantb 2*600MW Unit
Preparation of impact analysis report on weekly basis for any variation in the original scope of work.
Qinzhou Guangxi Coal PowerPlant
South of China Guangxi Province
My Job Responsibilities here includes:
- Civil works for the site work.
- Help in the preparation of Invoices.
- Preparation of material Requirement plan.
Mar 2005 to July2005 Job Title : Trainee civil engineer
Employer : Jian An civil construction company
Country : China
Project : Yin zuo Auto Malls
My Job Responsibilities here includes:
- Technical works support for the civil site works.
- Lining and some basic works.
- Monitoring site manpower.