Sivakumar Shenbagaraman resume

S.Siva kumar,

 

Off.Address:Maintenance Service Department, SABIC Petrokemya, Al-Jubail, Saudi Arabia

Mobil No-00966-59 8088182,
 
[email protected], [email protected]

Lead planning Engineer for Annual Turn
 
around/ Plant maintenance /Project in Oil,
 
Gas & Petrochemical Industry

 

 


Short Profile of Present company (SABIC-Petrokemya - KSA)

SABIC's manufacturing network in Saudi Arabia consists of 17 affiliates. SABIC is owned by the Saudi Government (70%) and the private sector (30%). Petrokemya is wholly owned affiliate of SABIC. Petrokemya is producing Ethylene, Polystyrene, Butene-1, Propylene, Natural Gasoline Butadiene, Benzene, Polyethylene, VCM &PVC

Current Position: Senior Planning Engineer- TMP (Leading May-2012 Olefin-1 & PVC Plants turnaround planning)

 

Experience Summary

 

  • Coordination with Maintenance & Operation departments for Turnaround preparation and execution.
  •  Resources (Man, Material & Equipments) planning for Turnarounds of Natural Gas liquefaction plant & Petrochemical Industries, The job scope is inclusive Pipe lines replacement, Static Equipments replacement,  Maintenance of Exchangers, Coolers, Boilers, Rotary equipments, Columns, Vessels and PSVs
  • Developing contract SOW, coordination with purchase group & maintenance for contracting activities and follow up with contractors for mobilization and execution.
  • Preparation of isometric drawings for Pipe line replacements.
  • Hands on Experience in Primavera 6.1 and SAP R/3 for MM, PM & PS Modules.
  • Execution of Annual Turnaround
  • Planning for daily maintenance of Petrochemical Industry.
  • Operation of Utility Equipments (Boilers, De-aerators, Compressors, A/C& chiller units, Water treatment plants and Diesel generators)
  •  Maintenance of Utility equipments & Tyre manufacturing machines.
  • Execution of Green field & Brown field Projects including site design.
  • TPM, TS 16949, ISO 14000, Quality Journey Experience.
  • Energy conservation activities
  • Liaison with Boiler inspector, suppliers and contractors.


 

 

Scholastic records

  • B.E., (Mech)from National Engg college, Madurai Kamaraj University, India, Passed out with 74.52% marks, Ranked I in the College in 1989-1993
  • MBA (Operation management) from IGNOU, New Delhi, India, with First Division in June’2008.

 

Certificate of Proficiency

  • Certificate of Proficiency on Boiler Operation Engineer under the Tamil Nadu BOE’s rules 1963

 

Training, Workshop & Seminars

  • SAP PS Module training (3 days )by SABIC training centre.
  • SAP PM Module training (10 days ) by SABIC training centre
  • MDRM End user training (3 days)by SABIC training centre
  • Turn Around Workshop-In Abu Dhabi, UAE from 30.03.08 to 03.04.08 with ADGAS TA team- Conducted by Shell Global Solutions (SGS).
  • Conference on Hydro carbon safety- PETROSAFE-2007 at Kochi, India, from 23.04.07 to 25.04.07, organized by National Safety Council, in technical collaboration with Petroleum and Explosive Safety Organisation, India
  • Power plant training-In M/S Wartsila Diesel India Ltd., Khapoli, India from 01.08.95 to 10.08.95.

Languages Known                

  • English, Tamil, Hindi, Malayalam

 

EXPERIENCE SUMMARY

 

Organisational unit

Designation

Duration

M/S SABIC Petrokemya, Al-Jubail, KSA

Senior Planning Engineer

2010-till date

M/S Equate Petrochemicals company, Reliability Maintenance Department, Kuwait.

Maintenance Planning Engineer- RMD

2009- 2010

M/S Descon Engineering, ADGAS Annual Turn Around Project, Das Island, Abu Dhabi, UAE.

Core Team-Sr. Planning Engineer

2007-2009

M/S Apollo tyres limited, North kalamassery, Ernakulam District, Kerala, India.

Associate Manager(Engg)

2005-2007

M/s MRF Ltd., Eripakkam village,

Pondicherry, India.

Senior Mechanical Engineer

1999-2005

M/s DCW  Ltd. (Petro chemicals), Sahupuram, Tuticorin District, TN, India.

Engineer (Mech-Captive Power Plant)

1995-1999

M/s Krupp Industries (I) Ltd., Tuticorin Thermal Power Project, Tuticorin, TN, India.

Engineer Trainee

1993-1995

 

 

 

Computer knowledge

  • Microsoft Word, MS Excel, MS Power Point, MS Project 2003, and Primavera P6.1
  • Having experience in  SAP R/3 Maintenance ,Project and Material Management modules
  • Intergraph Smart plant markup,(For Management of Drawings).

 

 

 TURNAROUND PLANNING EXPERIENCE

Descon Engineering Ltd, UAE, -ADGAS Annual Turnaround Project (Train 1& Boilers SD 2007 & Train 2 & Boilers 2009) - Core Team Senior Planning Engineer

  • Responsible for planning and scheduling for the work orders to be carried out in Annual Turnaround in the LNG plants consists of Heat exchangers, Columns, Vessels,  Propane & MCR compressors and GE turbines, Elliot make Turbine drives  60 bar & 250 TPH boilers, Fire water and Cooling water (Sea water systems),  Connected  Hydro carbon gas, Steam, Condensate, Air, Sea water pipe lines.

SABIC PETROKEMYA- TMP/Maintenance Support Department- TA Planning leader

  • Leading Turnaround Planning of 2012 Olefin-1 Plant and 2010 PVC/VCM plant Turnarounds.

Job Description:

  • Initiation Phase: Planning Turnaround preparation. Creating AR, WBS, Conducting Turnaround Initiation meeting, Forming Turnaround preparation team.
  • Scoping phase : Coordinating with all disciplines for TA scope collection, Scope review, challenging and issue preliminary job list.
  • Planning & Scheduling phase : Creation of work orders, Studying, understanding all relevant documents & conditions pertaining to the work orders and Preparing Isometric drawings with Materials list using SPF and SAP according to plant piping, painting and insulation specifications. Identifies and recommends requirements for specialized contractor work, preparation of job specification/job scope of contracts and coordinating bid evaluation as required.

Liaises with Maintenance, Operation,& Inspection Engineers to determine their resources requirements and plans required manpower, material , equipment and services for the successful accomplishment of jobs

Following materials take off and prefabrication before Turn around

Deployment of manpower & equipment schedules from Primavera. Preparation of Turnaround packages.

  • Pre-turnaround Phase: Kick of meeting with contractors, coordinating contractor & equipment mobilization, coordinating turnaround facilities. 
  • Turnaround Phase:Leading Turnaround meetings & Contractors meeting,Monitoring & making S-Curves for actual completion of work Vs schedule and initiates control measures to control deviation.Takes Health, Safety & Environment (HSE) lead in ensuring "safe systems of work" and "safe conditions" are in place within area of responsibility.
  • Post Turnaround Phase: Invoices verification, Critiques meeting, Preparation of Close out report and Project closing.

DAILY MAINTENANCE  PLANNING EXPERIENCE

EQUATE Petrochemicals Company, Reliability Maintenance Department- Kuwait

  • Responsible for planning for the work orders to be carried out in Utility & Ethylene Glycol Plants. Understanding and accessing the work notifications from process, Creating work orders, Planning work activities, resources ( man, materials & equipments) using SAP R/3 according to DOW Chemicals Global maintenance work procedure and EQUATE standards, preparing job packages consists of Work orders, Schedule, Safe Job plan, Drawings & relevant documents.
  • Advising scheduler to get maintenance schedule in Primavera-6 according to operations priority and resources availability.
  • Following up work activity co coordinators, Process activity co-coordinators, material controller and PPM co-coordinator to get the maintenance jobs as per plan.
  • Maintenance budget preparation and maintenance cost optimization.
  • Participating in maintain facility team meetings, to improve Department maintenance activities, improve reliability, reduce maintenance cost & improve HSE metrics.

 

OPERATION AND MAINTENANCE EXPERIENCE

Operation & Maintenance Equipments Summary

  1. Gas Liquefaction plant Heat Exchangers & columns
  2. Water tube and Flue tube boilers, Hot Water Generators, Deaerators.
  3. Chillers, Air handling units, Air Compressors & Cooling Towers.
  4. Steam Pressure Reducing stations and Condensate Recovery System
  5. Diesel Generators and Oil Purifiers.
  6. Water treatment plants consist of Clarifiers, MG Filters, Softeners, and Membranes.
  7. Hydro carbon lines, High Pressure Steam, Hot water, Chilled water, Cooling water and Fire hydrant pipe lines and Hot & Cold insulations.
  8. Effluent Treatment Plants.
  9. Single stage & Multi stage Centrifugal, Screw and Gear Pumps.
  10. Tyre Curing Presses and Tyre Balancing and uniformity testing machines
  11. Beverage bottling plants.

 

 

 

  1. M/s Apollo Tyres Limited.,

Planning & Execution of maintenance of 45”,55” & 65” Tyre curing presses , O&M of utility equipments like weishaupt burner mounted 14 Ton/Hr Shell max (Weishaupt burner controlled)package boiler and 13.5 Ton/Hr Westerwork boiler, 6 x 1100 CFM KG-Khosla air compressors, 240 TR chilling plants and water treatment plant.

Achievements

  • Reduced power cost by USD 27500 /annum and furnace oil cost by USD162500/year       (Reduced Specific Fuel consumption by 10%).
  • Reduced Oxygen scavenger chemical cost by USD 20000/annum.         

2. M/s MRF Ltd.

  • Planning & Execution of maintenance of 45”,48” & 65” Tyre curing presses, 46” Hydraulic presses, Tyre uniformity optimizers, X-ray machines, segment and non segment moulds for Radial truck and  passenger tyre curing,
  • Operation & Maintenance of utility equipments like 2x8 ton IAEC make package boilers, 1100 CFM air compressors, Freon compressor based A/C & Dehumidification plant, RO & DA water treatment plant and 2 x 1500 KVA Cummins DG sets.

Other relevant information

  • Actively involved in electrical and thermal energy conservation studies and implementation. (Savings 65000 USD /year achieved, due to study conducted and suggestion given by self).
  • One of the members for TPM Model machine, PM Pillar, Utility circle leader.

 

3. M/S DCW Ltd., (Petrochemical Industry)

Operation & maintenance of Wartsila make 18 V 32 E model diesel engines, Westfalia and Alfa Laval make oil separators, screw pumps, air compressors, single stage and multi stage centrifugal pumps and soot blowers, Thermax WHR Boilers, Reverse Osmosis plant and Hot water firedVapour absorption M/C .

PROJECT EXPERIENCE

1. M/s Krupp Industries (I) Ltd

Erection and commissioning of Coal Handling Equipments like Belt conveyors, Crushers, Hoppers etc. Fabrication and Erection of Dust Extraction System and Dust suppression system for coal handling systems.

2. M/S DCW Ltd.,

Acting team member in Green field project of captive power plant including erection and commissioning of  5 no. of 6 MW Wartsila DG sets, westfalia Separators, thermax make 950 sq.m  waste heat recovery boilers, 57 m height self supported chimneys, fire hydrant system. 3x600 cub.m FO storage tanks and auxiliaries for captive power plant.

Erection and commissioning of Thermax make 240 TOR HWF Vapour absorption machine and 2 x 18 cub.m Reverse Osmosis water treatment plant and Performance testing of Membranes.

3. M/s MRF Ltd.

  • Erected and Commissioned 15  Nos  of 48” Curing press with steam, hot water and cooling water pipe headers and connected lines  by 4 months.
  • Erected and Commissioned 16 Ton Shellmax boiler- 1no, Hot water high pressure de-aerator with steam PR stations , 1100CFM air compressors- 2 Nos, Tyre uniformity machine- 2 Nos. 80 TR chilled water system and Dehumidification Air Handling unit for creel steel wire storage room.
  • Replaced 1000 KVA DG set by overhauled engine.

4. M/s Apollo Tyres Limited.

  • Erected and Commissioned 14 Ton Shellmax boiler- 1no, Replaced westerwork boiler burner by weishaupt Germany burner and Furnace oil, Air systems in 7 days.
  • Being involved in Project proposal, planning, estimation of new proposed 180 ton/day Tyre plant at Irapuram Rubber Park.
  • Proposal, Erection and commissioning of soft water treatment plant.

Strengths:

  • Cost conscious and self initiative.
  • Leading the team by setting self as example.  Development of sub-ordinates by training and delegation of authority & responsibility.
  • Systematic approach for problem analyzing and solving.

Personal profile:

Date of birth & Age                : 28.07.1972, 39 Yrs. 

Marital status                          : Married

 

Nationality                              : Indian

 

Reference:

  1. Eduard Van Grootveld, Planning Manager-PDM ,  

      Mail: [email protected], Mobil No: +971 50 661 0681

  1. K.V.M.Sundaram- Core Team leader- ADGAS thro’ Descon Engg

      Mail:  [email protected], +971504105420

 

S.SIVA KUMAR