Assistance Planner, Zelan Priamanaya Joint Operation, coal fired power plant 1 jateng 2x315 MW rembang indonesia

START Date
END Date

Company                  : EPC JO Zelan Priamanaya Joint Operation

Work Location        : PLTU 1 Jawa Tengah Coal Fired Power Plant 2 x (300-400) MW

                        Rembang, Indonesia 

Period of Service    : November, 2007 – December, 2009

Job Title                    : Ass. Project Planner/Project Scheduler 

Responsibility Included:

 

Image removed.  Monitoring Progress at site of Bore Piles & Marine Steel Piles then report to Construction Manager and HQ.

Image removed.  Monitoring Progress at site as All Civil Works Construction.

Image removed.  Monitoring Progress at site of Mechanical Works as (Boiler and Turbine).

Image removed.  Monitoring Progress at site of Electrical Works as Switchyard 150 KV.

Image removed.  Resolving any unexpected technical difficulties, and other problems that may arise.

Image removed.  Prepare Status Report including S-Curve, Summarizing progress against planned then report to owner and HQ.

Image removed.  Perform production rate and planned progress analysis.

Image removed.  Co-ordinate planning and programming activities with sub-contractors and suppliers.

Image removed.  Taking picture on the site if any the start or finish works.