Sherif Ghaleb resume

 

 

Image removed.Senior Planning / Project Control Engineer, PMP®

Sherif M. Ghaleb Nasr

[email protected]                                                                              

+ (966) 56-965-3344         

 

 

Objectives:

Seeking career-oriented position as a Senior Planner in company reputable as yours, where my academic background, training experience & communication skills can be applied and further enhanced.

 

Practical Experience:

Image removed.

                    Saudi Oger Company LTD

                             (July-2009 to Present)

 

Image removed.


The project:     Saudi National Guard Housing

Location:           Riyadh, KSA

Project budget: SAR 7 Billion

Client:               Saudi National Guard

Consultant:       Dar Al Majed Consultant, Hill International

Role:                   Senior Planning / Project Control Engineer

 

Image removed.The project:     Princess Nora University for Women (PNUW)

Location:           Riyadh, KSA

Project budget: SAR 12 Billion

Client:               Ministry of Finance; Ministry of Higher Education

Consultant:       Dar Al Handasa Consultant

Role:                   Planning Engineer

Responsibilities:

  • Time management:
  • Creating WBS, Activities Code & ID & Sequence Activities
  •  Estimate Activities Duration & Develop Time Schedule Baseline Master & Detail for EPC Project
  • Monitor Schedule by generating performance report, Variance report, Trend report
  • Control Schedule by recommend corrective action for crash/Fast track the project to save or recover time and implement it to the schedule
  • Create a Forecast Activity report
  • Prepare time claims
  • Cost management:
  • Load cost to activity
  • Create a cash in flow and cost histogram
  • Coordinate with cost control to estimate and provide cash out histogram
  • Generate the invoice and review it with the Client for approval
  • Monitor cost by generating Earned Value calculation
  • Coordinate for a cost forecast report out and create a cost forecast report
  • Human Resource & Procurement Management:
  • Estimate Activities Resource and loaded to the schedule
  • Generate Resource histogram
  • Create HR & Procurement forecast report
  • Attend progress & Status meeting with the Client, Subcontractor, Top management & Site responsible

                               -----------------------------------------------

 

Image removed.

                    Talat Moastafa Group          

                             (Feb.-2009 to July-2009)

 

The project:      Madinati (city project)

Image removed.Location:           Cairo, Egypt

Project budget:EGP 1 billion

Client:              Talat Moastafa Group          

Consultant:      ECG Consultant

Role:                  Planning Engineer

Responsibilities:

  • Time management:
  • Sequence Activities & Develop Time Schedule Baseline
  • Monitor Schedule by generating performance report, Variance report, Trend report
  • Recover Schedule
  • Create a Forecast Activity report
  • Cost management:
  • Load cost to activity
  • Create a cash in flow and cost histogram
  • Monitor cost and generate cast performance report
  • Create a cost forecast report
  • Human Resource & Procurement Management:
  • Load HR & Procurement to the schedule
  • Generate HR & Procurement histogram
  • Create HR & Procurement forecast report
  • Attend progress & Status meeting with the Subcontractor & Site responsible

                               -----------------------------------------------

 

 

Image removed.                      Core Construction Company

                                (July-2008 to Dec.-2008)

 

The project:                 Industrial (Factory, Hangers)

Location:                      Dubai, UAE

Total Projects budget: DHS 300 million

Role:                             Planning Engineer

Responsibilities:

  • Time management:
  • Creating WBS, Activities Code & ID & Sequence Activities
  •  Estimate Activities Duration & Develop Time Schedule Baseline for EPC Project
  • Monitor Schedule by generating performance report, Variance report, Trend report
  • Create a Forecast Activity report
  • Prepare time claims
  • Cost management:
  • Load cost to activity
  • Create a cash in flow and cost histogram
  • Create provide cash out histogram for project estimation
  • Generate the invoice and review it with the Client for approval
  • Monitor cost by generating Earned Value calculation
  • Coordinate for a cost forecast report out and create a cost forecast report

 

  • Human Resource & Procurement Management:
  • Load HR & Procurement to the schedule
  • Generate HR & Procurement histogram
  • Create HR & Procurement forecast report
  • Attend progress & Status meeting with Subcontractor, Top management & Site responsible
  • Create Tender Baseline With Resource & Cost Histograms

                               -----------------------------------------------

 

    Master Civil Construction Company                

         (June-2006 to July-2008)

 

The project:                 High Rise Building & Mosques

Location:                      Sharjah, UAE

Total Projects budget: DHS 500 million

Role:                             Planning Engineer

Responsibilities:

  • Time management:
  • Creating WBS, Activities Code & ID & Sequence Activities
  •  Estimate Activities Duration & Develop Time Schedule Baseline
  • Develop Time Baseline for EPC Project
  • Monitor Schedule by generating performance report, Variance report, Trend report
  • Control Schedule by recommend corrective action for crash/Fast track the project to save or recover time and implement it to the schedule
  • Create a Forecast Activity report
  • Prepare time claims
  • Cost management:
  • Load cost to activity
  • Create a cash in flow and cost histogram
  • Coordinate with cost control to estimate and provide cash out histogram
  • Generate the invoice and review it with the Client for approval
  • Monitor cost by generating Earned Value calculation
  • Coordinate for a cost forecast report out and create a cost forecast report
  • Prepare cost claims
  • Procurement Management:
  • Load Procurement to the schedule
  • Generate Procurement histogram
  • Create Procurement forecast report
  • Attend progress & Status meeting with the Client, Subcontractor, Top management & Site responsible

                               -----------------------------------------------

 

 

 

Mahfouz Modern Building Factory                

         (May-2005 to Jan.-2006)

 

The project:                 Precast Concrete

Location:                      Dammam, KSA

Total Projects budget: SAR 2 million

Role:                             Planning & Technical Engineer

Responsibilities:

  • Time management:
  • Creating WBS, Activities Code & ID
  • Sequence Activities, Estimate Activities Duration
  • Develop Time Baseline for Factory & Erection
  • Monitor Schedule by generating performance report, Variance report, Trend report
  • Control Schedule by recommend corrective action for crash/Fast track the project to save or recover time and implement it to the schedule
  • Create a Forecast Activity report
  • Attend progress & Status meeting with the Client, Subcontractor, Top management & Site responsible

                               -----------------------------------------------

 

H.S.D.C consultant                 

         (Aug.-2004 to April-2005)

 

The project:                 Infrastructure & utility Plants

Location:                      Mansoura, Egypt

Role:                             Structure Design Engineer

Responsibilities:

  • p

 

Academic Education:

University:     Bachelor of Science of Civil Engineer (construction), El_Mansoura University, Cairo, Egypt (July, 2004).

 

Professional certification:

PMI          :     PMP®certification, (Feb., 2012)

 

Skills and Courses

Courses:

  • Professional in AutoCAD 2D (Oct. 2003)
  • Primavera P3 (April 2005)
  • FIDIC Course in Society of Engineering, UAE (Feb. 2007)
  • Primavera P6 (June 2009)
  • PMI’s Project Management Professional (PMP) exam preparation course (Oct. 2011).
  • MS Office

Hobbies:

Net Surfing, Gaming, Puzzle Solving, Internet Chats, swimming & Football

Languages:

Arabic:   Mother tongue

English:  Excellent knowledge of written & spoken (TOEFL)                                                                                             

 

 

Personnel Data:

Date of Birth:    

April 28, 1982.

Religion:          

Muslim

Nationality:         

Egyptian

Marital Status:   

Married

 

Driving license:

 

Valid (Egypt, UAE & KSA)