Lead Planner

Lead Planner

Lead Planner, Grinaker LTA, Polifin PVC Expansion Project

START Date
END Date
Experience Hours (Planning & Scheduling)
5850
Experience Hours (Cost Management)
300
Experience Hours (Forensic Analysis)
150

Group projects planner. Co-ordination, checking & detailing of all programs for various project sites, that include a hands on approach. Liase with client, suppliers & fabricators. Going to various sites and fulfilling planning functions, to reschedule and re evaluate environment with changes in scope and contract.
1996 Namdeb Floating Treatment Plant. Level 4 programs for fabrication of barge, structural steelwork, platework and piping.
1996 Goldfields Refrigeration Pipeline. Installation of pipeline for Mine chilled water system.

Lead Planner, AMEC Power & Process Europe, Hole House Underground Gas Storage Phase 3

START Date
END Date

Lead planner on underground gas storage EPC project for key client EDF Energy.

Responsibilities include maintenance of Project Programme in Primavera P6, Supervision of the Progress Measurement database and Earned Value reporting.

Lead Planner, Ghelamco, Marynarska Business Park

START Date
END Date

Lead Planner

*Marynarska Business Park

Main duties:managing investment documentation,production of detailed target / baseline construction programme, monitoring and updating progress, regular report to construction director, critical path analysis using Primavera P6 software. Planning advise and support to project team were required re-scheduling.

Lead Planner, Network Rail, All Great Western Region Projects

START Date
END Date
Experience Hours (Planning & Scheduling)
1000
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
50

November 2003 to May 2004
Network Rail – Lead Planner/Programme Controls Manager     
Rail
Lead Planner for Investments delivery division covering Signaling, Telecommunications, Electrification and Plant Projects. Responsibilities include the supervision of all planning staff, ensuring that processes are followed and monitoring data/schedule integrity and producing reports for senior management.

Lead Planner, Shapoorji Pallonji & Co Limited, Building & Infra Works

START Date

Current Role Lead Planner

  Key Responsibility :

 

  • Prepare and update Project Schedule based on the contract.
  • Set work program and target milestones for each phase based on the project plan.
  • Forecast Manpower requirements, Material Procurement, Formworks movements and Monthly Cash flow.
  • Monitor critical activities based on the project schedule and advise project management.(Weekly R

Lead Planner, Alstom, Drax Biomass project

START Date
END Date

2001 to date  Alstom Power - Lead Planner for a number of years working on UK and overseas projects. From design & supply projects to major ’Turnkey’ Projects for the build of new gas and oil fired stations to Biomass co-firing projects and Capacity increase Projects. Experience of planning with coal power station projects.  Specific projects are Arnot Power Station Capacity Increase project (Euros 36.233M) in South Africa, Drax Power Station Biomass co-firing project (£48.28M).

Lead Planner, ABB, Various

START Date
END Date

Planning, management and programme co-ordination of contractor’s / client’s networks and progressing and reporting against detailed procurement, construction, fit-out and commissioning programmes. Review, co-ordination and control of technical contractor’s outline and detail design programming requirements.