Search

Earning Progress Credit for Deliverable

Forum Topic

Hello Everyone,I am working in Oil and Gas Sector on the Main Contractor Side. The senario here is we have a Contract with Cleint which says the Client Review period is 5 Calendar Days after Issue of Deliverable.If the Client didnt respond back in 5 ...

Oct 3, 2018

Like

Forum Topic

Hi AdminIt's time we had a "Like" box to tick on a post.Best regardsMike T.

Oct 3, 2018

'Multiple Float Paths' with P6 Web locks up

Forum Topic

Do you use the 'Multiple Float Paths' functionality within the scheduler of P6 Web (EPPM)?   I'm using R8.2 (B0869) 12.13.2011.1223 and am finding that it locks up (wont re-schedule using a new target milestone), after a single use.  It can only be u...

Oct 3, 2018

Risk managment for improvements

Forum Topic

Hello everyone,I am director of the business process department in the biggest courier company in my country.We have thousands of processes which are conneced between them and connected with the processes in the managment processes of the company. We...

Oct 4, 2018

Primavera P6 17.12.1 is NOT calculating correctly!

Forum Topic

I have used P3, P5, and P6 for many years, but this latest version of Primavera P6 needs URGENT REVISING! It is really troublesome, and I will AVOID IT as much as I can from now on! 1) Even though the Start Date considers constraints entered after th...

Oct 4, 2018

Baseline Schedule Submitted after Contractual Deadline?

Forum Topic

Hi all,(I'm not sure if this is the right place to ask about this issue, if its not please let me now)I have been assigned to a project with the contractor to create a baseline for it after the contractual deadline. When I was finished with the sched...

Oct 6, 2018

Swimlanes Project Process

Forum Topic

Hello,I'm looking for a swimlane diagram of the Project Process (i.e. from PMI) to assign clear accountabilities and clarify sequencing.do you have any basis I can start from?Kind Regards,Lorenzo 

Oct 8, 2018

Simple planning level-0 connected to Outlook

Forum Topic

Hello,I'm managing a programme of 30 projects and I'm using a macro planning which highlights project phases (Initiation, Design, Execution, Closure) and sanctioning Milestones + Reviews.I would understand how to ease my job of programme coordinator ...

Oct 8, 2018

Change Duration when adding extra Resource

Forum Topic

Hi All,What settings must I use to get P6 to change Activity Duration when I add extra Resources?Lets say I have I have a 10 day activity with 1 Resource on it and 100 units, when I add an additional same Resource I want the duration to reduce to 5 d...

Oct 8, 2018

On-Going Progress Gap

Forum Topic

Hi Guys,Just like to know why is there a gap in updating or progressing on an activity on on-going projects? Also is there a way to mitigate this?Another, can you guy provide reference guide in making or doing an Delay Impact Schedule?Thanks in Advan...

Oct 9, 2018

Rebooting my planning career

Forum Topic

23 years ago I left the construction industry & became a fire fighter. I’m now a mid level senior officer. I’m considering starting up a one man construction planning consultancy. If it works out I may leave the fire service at some point. I complete...

Oct 11, 2018

How do you show 3 baselines on one bar?

Forum Topic

HiMy manager has asked me to show 3 baselines on one bar. Shown me the output One bar for one activity, with 3 colours per baseline overlapping to show delay - rather than the usual stack arrangment

Oct 12, 2018

Resource Linking - good/bad?

Forum Topic

I'm kicking off the planning of a 200,000 hr shutdown due in 12 months. Previous shut downs here have used extensive resource logic between physically unrelated activities as a way of manually resources.I'm not a fan of resource linking, I'd rather u...

Oct 15, 2018

Show Completed Task as Critical

Forum Topic

Hello,I'm looking to analyse the critical path of a part-completed programme for a project, however, tasks that are 100% complete or have been progressed do not show up as critical.Is there any way of showing progressed items as critical without havi...

Oct 15, 2018

Starting career in planning/cost control

Forum Topic

Hi,I'm currently a junior civil engineer (2-3 years experience) working for a consultancy, and have developed in interest in project planing/cost control as a future career. I'm just wondering what can I do to become more knowledgeable in this area?I...

Oct 15, 2018

Combination relationship

Forum Topic

In Primavera P6 we can have a combination relationship i.e an activity can have same predecessor twice, once with Start-Start relationship & another with Finish- Finish relationship. Is it a good practice to have such type of combination relationship...

Oct 15, 2018