Search

1 day duration - finish day is different from Start day

Forum Topic

This may be a simple question but why if a task has a 1 day duration (8 hous) is the finish day the next day, e.g. Start day - 4/13/2016 - duration 1 day == finish day is 4/14/2016.  Logic tells me that the finish day is 4/13/2016.   Is there a way t...

Apr 13, 2016

Airport runway strengthening

Forum Topic

Hi, I am currently involved in an expression of interest for a regional aerodrome upgrade. I don't have any airport project exprience but I have done a lot of road jobs.One of the scope of works is to strengthen the existing runway from PCN 18 to PCN...

Apr 15, 2016

Set up password to MS project file

Forum Topic

Good day Dear Ladies/Gents,It is big pleasure for me to join this forum.I am beginner on MS Project and need your advise on how to set up password for MS Project file. So only I (or person knows password) can modify file and rest personnel who has ac...

Apr 15, 2016

Font and Backround Color change

Forum Topic

Dear All,While I am trying to change FONT and BACKROUND colour on task or subtasks somehow prevous changed tasks return to origianl colour (black and white) on MS project file. Even when I select 10 task and sub tasks for colour changing some of them...

Apr 15, 2016

Estimate to Complete Cost

Forum Topic

Dear All,I need some clarification regarding the calculation of 'Estimate to Complete' in Primavera P6 (ver 7 to be specific). In one of my updated baseline I noticed that for some of the completed activities the ETC is shown to be zero but at the sa...

Apr 17, 2016

Estimate to Complete Cost

Forum Topic

Dear All,I need some clarification regarding the calculation of 'Estimate to Complete' in Primavera P6 (ver 7 to be specific). In one of my updated baseline I noticed that for some of the completed activities the ETC is shown to be zero but at the sa...

Apr 17, 2016

Inquiry : Planning by Quantity not Duration

Forum Topic

Hi everyone , I have a question How can I make P6 to calculate the original duration by itself ( To give it a quantity and Productivity rate ) Duration = Quantity * Productivity rate any body can help me please Thanks 

Apr 18, 2016

Out of Sequence

Forum Topic

Any method to put on sequence all those out of sequence after you update the programme. Normally I did 1 by 1 from log register and chenge the relationship of thos activity that out of sequence. Pleased advised. Thanks

Apr 18, 2016

Global Change Not Working

Forum Topic

Here is the situation.  I am trying to take an in progress schedule and use it for a new project.  The unstatused baseline is not available, only an in-progress version.  Normally this is no problem, I simply run a global change for activity status n...

Apr 18, 2016

Progress Tracking for MEP Progects

Forum Topic

Dear All,I started working as a Planning Engineer from Aug-2015. Till today I'm facing problems in tracking the work progress from site. Whenever I request for site progress updates I'm not getting any proper updates. The site people says that its th...

Apr 19, 2016

Formatting "Group By" Bars on Gantt Chart (MSP2010)

Forum Topic

Hi,Not been able to find an answer to this on the forum, so here goes.I have a detail schedule that is using groups to set up a Level 0 schedule. There are 7 phases, with each phase containing tasks for four elements (Design, Approvals, Construction,...

Apr 19, 2016

Project Charter

Forum Topic

Hi Planners,who creates the project charter and who approves it?Best,Muataz

Apr 20, 2016

Schedule activities that can be executed in any order

Forum Topic

Hello,I have just made my way into a precast production company as a project planner. My role is to plan the erection process at site. That is I have to plan which elements are to be erected on which dates and so on and my company wants me to do it i...

Apr 20, 2016

Schedule activities that can be executed in any order

Forum Topic

Hello,I have just made my way into a precast production company as a project planner. My role is to plan the erection process at site. That is I have to plan which elements are to be erected on which dates and so on and my company wants me to do it i...

Apr 20, 2016

How can I make easy project reports for my customers?

Forum Topic

If you are a project manager, you probably know the problems of creating a fast and meaningful report about the work your team has done.Well I think the time is over soon! We from Projecker located in Stuttgart, Germany, develop an online tool, which...

Apr 20, 2016