Search

Total Float

Forum Topic

In my project, There are three WBS. The first and third WBS are about project start and finish procedures. And the second WBS is about all project works of different desciplines. Is there any possible technique in P6 to identify the total float based...

Dec 16, 2018

PMIS

Forum Topic

Hi All,Could any one recommend me with an excellent Project Management Information System (PMIS)? I need this for company projects and need to be used by project managers and planners.best,Muataz

Dec 16, 2018

Remaining Units Update Automatically

Forum Topic

I've imported a new project and I have started to update the progress. I've had a few problems:1. When I update the actual units on an activity the actuals are added on to the at completion instead of taken away from at completion units. In other pro...

Dec 17, 2018

Resource cost rounding

Forum Topic

Hello Vladimir,Materials in Spider have an option called Discrete Consumtion which rounds up the consumtion of the material (granted the Backload consuption is set to No).So here is my question, is there a way to do this with resources?Example: Backh...

Dec 17, 2018

User defined columns

Forum Topic

Hi,Does anyone know if its possible to create user defined columns that you can populate from drop down lists?looking to create  a columns where I can have units such as kg, tonne, m , m2 etcRegardsChris

Dec 18, 2018

Spider Macros

Forum Topic

Hello Vladimir,in the latest versions of Spider Macros have been introduced as a new functionality. There are two types of macros:Internal, from what I understand these are macros applied at the project (file) level;External, from what I understant t...

Dec 18, 2018

Baseline

Forum Topic

Every tree or two months, my Schedule Variance increase, my planner modify the baseline eachtime two reduce the variance, is it correct to do it? and if it's correct in which case we have to do it please?

Dec 24, 2018

(2019) Happy Festivities

Forum Topic

Hello everybody,Best wishes to the PP's community as our calendars approach the 2019 switch in approximately two weeks.For the planners taking christmas as a day off, merry christmas and enjoy the days out!  For all the others, planning or not, happy...

Dec 24, 2018

Schedule Percentage complete

Forum Topic

Greetings to everyone. Is there any possible technique in primavera to get all the schedule % complete for each day ? Thanks in advance.

Dec 25, 2018

Historical Data of Projects

Forum Topic

Hi,I would like to seek the expert advice here as to what sort of historical data a planner should have readily on hand by the end of a project, to better prepare for the next one. This would include things like Scope / Rates / Costs.Are there any ot...

Dec 27, 2018

How to erect a recovery schedule

Forum Topic

Hi every body,I'm looking for a methedology to build a recovery schedule, because we are late and a lot of gaps was noted and our contractor was very furious, what is the best solution please ?

Dec 28, 2018

Scheduling

Forum Topic

Can someone tell me the maximum number of activities for a single planner to maitain efficiently ?ThanksRoberto

Jan 1, 2019

Filtering activities

Forum Topic

Hi,In our project plan, I want to filter acitivities under Podium - Level 01 (Activties circled in attached image). Please help.[[wysiwyg_imageupload:6438:]]

Jan 4, 2019

Remaining Late Unit tabulated based on Early Finish Date

Forum Topic

Hi.Basically the situation is I need to do a revise programme, so I used the latest updated schedule, revise and re-baseline it. So from the revised programme, I input new resources as I need to generate S-Curve with 3 main elements which are Planned...

Jan 6, 2019

S curve Formula

Forum Topic

During my experience in few company, I found a kind of table to draw our s-curve, you can choose a number of period and you have the forcast corresponding of this period, the periode can be (hour, day, week or month), for exemple :Number of period 4 ...

Jan 7, 2019

Planner duties

Forum Topic

I want to do what is the duties of the planner in a company, what he has to do ? for exemple is it in his duties to prepare the sheet of payement 

Jan 8, 2019

GLOBAL CHANGE - WBS

Forum Topic

Hello frineds, Hope you all are doing great.I Have construction Acitivtes (Physical %) which are assinged with labor Units (Direct) & Cost not loaded. That means during the update of scheudle I will have BL Units, Planned Units, Earned Units. Now I w...

Jan 10, 2019

Loss of WBS Name when importing into P6 from MS Excel

Forum Topic

Hi I am importing an MS excel file into P6. I have no issues with this.However, when the excel file is imported, the WBS Name chages to the Master file name.I cannot sort and filter the WBS in P6 as the WBS is lost.Any help and suggestions would be a...

Jan 10, 2019