Recovery Schedule
Forum TopicI was requested from the consultant to make a recovery schedule on my latest updated , it show delay 42 days on the end of the project .what should I do ?
I was requested from the consultant to make a recovery schedule on my latest updated , it show delay 42 days on the end of the project .what should I do ?
Dear all, I having problems to retrieve all data from my dead laptop hard disk and transfer to new laptop. Lucky the hard disk still ok, The version P6 installed in the previous laptop is P6 Ver 8.3.2 and Database using Oracle XE. Please guide me ste...
hope it helpshttps://datamonkeysite.com/2017/01/17/how-to-import-progress-to-primavera/
While importing an xer file an event code was displayed (AVAAO-3660-0) and I was unable to complete the import. When I ran the exception report the message stated that it was "Access violation at address 00B09AOE in module 'PM.exe'" what do I need ...
Hi Everyone, if anyone knows a way out of this I would highly appreciate it.I wanted to backup my projects (over 100 projects) so I can transfer these projects to another computer with an higher version of P6, so I tried opening like 15 of them to ex...
Hi all, we have a currently running version of P6 R8 that is failing so I have attempted to create a new one. I have created a new server and installed SQL 2016 express and configured this. I have then installed P6 on the server, and it can connect...
Hi, I have the following question, on which I couldn’t find and answer in google. How to make a task with flexible duration, which will fill the gap between other 2 tasks and will automatically adjust it’s length: Example Task1: Deliver building mat...
Defining a 24 Hour Calendar for scheduling relationship lag works well to schedule the seven day weekly curing of material. The critical activity definition, however, may require adjustment. If you are not monitoring activity constraints then define ...
Accurate estimating is a challenge, as you are typically attempting to predict the future based on past experience and limited data. Read More http://ow.ly/zP2r308bW7J
Dear Sirs,Greeting!My apology if my question is already discussed before.Question:My client require each activity of my schedule to be LOADED WITH COST OF RESOURCES. i.e.A. Labor, Material & Equipment needs to be loaded with PRICE/UNITB. BUDGETED COS...
Hello,I was mentioned that I could do elapsed time in Primavera, but I cannot find anything in relation to how to do it.I have a project which is 95 working days long. I have created another schedule with a different start date and now some acitivite...
Hi,Does anyone know how to obtain EC Harris's Work Activity Norms Handbook?Thanks in advance.Best regards,Rinus Mijnsbergen
I am in the process of preparing an impacted schedule. For which, I need to break single activity of my baseline schedule into multiple due to constraints experienced during execution.Foe example. In my baseline shcedule i considered single activity ...
Attend for free - A Brief History of Portfolio and Project ManagementFeb. 8, 12pm-1pm ET
Here are 10 metrics can help you assess your performance as a PMO, and spot areas where you can increase the value and services you offer to your organization http://ow.ly/99jK308kRI4
HiOur asset has just been annouced to be tupe'ed across to Enquest - any gen on Enquest?
Here's a great primer on how to do stacked histograms in P6 Professional http://ow.ly/rGcj308pw8v
Good evening,I have been approached by a PM that I support who has asked a question of which i am unsure how to answer.The question is about applying a single risk against multiple schedule activitieswould the best approach be to breakdown the over a...
Here's how to assign a firm fixed price (lump sum) costs to activities in Primavera P6 EPPM http://ow.ly/NYsL308uciu
Hi all,We work in a massive single project with tens of thousands of activities. Multiple users create hundreds of global layouts and filters.I'm a relatively new user and haven't found an answer to these challenges ...Is there a way to set favorite ...