Excel Programme
Forum TopicHi, I have one question. If I submit a programme from excel, with no link, update. Is that document recognise during arbritation or court ? BR
Hi, I have one question. If I submit a programme from excel, with no link, update. Is that document recognise during arbritation or court ? BR
I need to prescreen candidates for a Scheduling position requiring solid P6 skills, prior to sending them on to the hiring manager. I've never used Primavera myself. Can you share with me a few basic questions to determine if a candidate really knows...
All, I am managing a fabrication subcontractor who is delivering weekly schedule updates to me in a PDF and P6 XER file. I import the P6 file into my P6 software in a new EPS node with only this single project in the node. I use the "update existing"...
Hi,In the link properties dialog box, there is a field called "Kind" which includes four kinds:Mandatory,Discretionary,External,Temporary.How are these kinds used?Best regards,Carlos.
Anyone can advice how to insert approval box in MS Project
Hi: When I update the data date in my P3 schedule, My steps as follows: 1. update all activities weekly 2. update data date weekly 3. schedule Problems: The early finish dates (already actual started activities) also prolong one week after I updated ...
Anyone planning to take their PMP or PgMP exams needs to be aware of the following. PMI have announced a major change in the PMP examination as at 31stAugust. If you have completed or are completing a PMP course you have 12 weeks left to take the ...
hi friends...after i revised a program, got the few activities in the end as critical.how can i remove/increase the float, so that to make it non critical.thanksfaizz
Hi Planners, I am seriously looking for a job in UK (I have valid visa). Finding hard to get a job here. Can anybody help me by listing out the best job websites more suitable for planning engineers in UK to browse with. Great thanks in advance.W...
Hi Primavera Experts, Anybody who can help me adjust the Spending Plan date to 6 years since the date only show 4 yeras. My project is 6 years and I want to encode my spending plan. Thanks, David
Hi Admin Marcia Lowry is posting spam on the forum. As is Johnny Bynum and Rodney Night Best regards Mike T.
When my contractor submit updated schedule he change sequence due to non availability of work front which is planned in baseline. Is this correct procedure ?Please advise me. Thanks in advance
Guys, can anyone help me solve my problem in importing relationships in P6...this error always come out whenever I import excel spreadsheet relationships to P6, thus importing is not made. Thanks, Ariel [[wysiwyg_imageupload:518:]] [[wysiwyg_image...
I've joined a company as a scheduler and their philosophy doesnt make sense to me. They tell me if the activity is completed, relationships doesnt matter. For example, Activity A is predecessor to Activity B with FS relationship and no lags. They say...
I've joined a company as a scheduler and their philosophy doesnt make sense to me. They tell me if the activity is completed, relationships doesnt matter. For example, Activity A is predecessor to Activity B with FS relationship and no lags. They say...
Just wanna highlight that the Password recovery system is not working,I can login to my profil using the one time access but i cannot change the password as it will give me an error "username/email has been registered". Currently i'm login to PP usin...
A ridiculously easy question - How do I switch onlinks in MSP? Im new to this software and I cannot for the life of me find where to switch the links on and off. I cant find a search box for the forum, the MSP help files are no good and even google ...
Hi Ya Was wondering if anyone could help me on this one. I am currently exporting a plan from P6 using the PM XER version 5 option (have also tried using contractor version 5), when the plan is then imported into our clients system (they are using P3...
Guys I need some help...I am working in P6 in my office and exported my schedule in xer format so I can work at home. After importing the file in my laptop, I noticed that the durations have been changed as well as the start/finish dates(calendar set...
Typically, when reviewing contractor schedule, I import their newly submitted file into the existing file that we maintain for that project, but when doing so, if the contractor has made any changes to the expenses during the update, they seem to add...