Search

Over allocation but under resource limit

Forum Topic

 Issue with P6 showing over allocation to things under the limit (see pic).  These are multiple resources combined.  Why is it showing over allocation when the resources are under the limit?  Any help would be great. [[wysiwyg_imageupload:4951:]]

Aug 15, 2017

changing the activity links and lags

Forum Topic

I m trying to review the MS schedule submitted by the Contractor, i noticed that he is changing the activity links and lags in the updated monthly schedule, does anyone have a spreadsheet or a certain method to review the links I tried exporting the ...

Aug 16, 2017

Works not reflecting accepted programme

Forum Topic

Hi I hope this has been posted in the right place...I have a situation where a contractor has had a clause 31 programme accepted however from day one the construction team are undertaking works in a different sequence... they clause 32 is due in 3 we...

Aug 16, 2017

WBS Schedule Pro Software and WBS Charts

Forum Topic

Here's a quick tip on how to make viewable WBS charts of your schedule for presentation to stakeholders using WBS Schedule Pro and WBS Charts http://ed.gr/dj7v

Aug 17, 2017

Multiple productivities in one activity

Forum Topic

Hi,    I'm trying to set up a Primavera Project for a future sensitivity/Monte Carlo analysis, therefore, I need to automatize the current schedule.     I have two activities running in paralell. Activity 1 is shorter than activity two and once it fi...

Aug 17, 2017

Progressing Milestones in the Spreadsheet

Forum Topic

When I log in as admin I can progress milestones in the spreadsheet, but when I log in as a user inside of a security group I have to progress up to 100% complete on the Gantt Chart and then change the date. The error reads that I do not have suffici...

Aug 17, 2017

Planned Resources Analysis Monthly

Forum Topic

Hi,Currently I'm preparing planned resources (machinery & manpower) required for the project in monthly frequency. However, there are two ways in assessing the planned and resources (perhaps different user different method). The method (in my opinion...

Aug 21, 2017

Filtering by Trades Contractor

Forum Topic

Hi All, Is it possibel to filter by trades contractor? I am currently using version 13.0.02.069 of Asta Thanks

Aug 22, 2017

MSP negative float and constriant

Forum Topic

Hi,I was analysing a schedule for a contractor. The final milestone (constrained finish on or before) has a float of -78 days and a finish of 1 Jan 15. If I remove this constraint I was expecting the end date to move by 78 days to Middle of March. In...

Aug 22, 2017

Urgently need help with my thesis: 3-4 minute survey - Please help!

Forum Topic

Hello, If you could help me out, I'd be hugely grateful! I'm urgently trying to capture some data for my research, I have created a short survey which can be found here: http://bit.ly/2ioYgCR The survey should take no longer than 3-4 minutes, dependi...

Aug 23, 2017

Layouts with built in filters

Forum Topic

Morning all, I've had a layout shared with me with filters built in, however I can't see how the filter works.  When I go to filter it shows "custom filter" but when selected it shows no filters selected for me to interrogate.  I've noticed this morn...

Sep 16, 2021

Milestone and Constraints

Forum Topic

I'm wondering wha the best practice it for this issue. Here is a simple exampleComplete Roof (Agreed owner milestone) 1 March 2022. Constraint is "Finish On or Before".It's predesessor activity is Install Roof and Flashing.  If this activity is showi...

Sep 16, 2021

Tracking Predecessors and Successors in complex MSP Schedule

Forum Topic

I'm in the process of creating a Schedule which is increasingly becoming more complex with more tasks and scope being added daily, noting P6's "Go To" function allowing you to trace up and down paths of successors and predecessor paths, is there a si...

Sep 17, 2021

Financial Management in Primavera p6

Forum Topic

Dear ExpertsCan we use P6 for financial forecasting? Financial forecasting & planning for company's.I was asked by my boss if we could use p6 for our company's financial forecasting & planning. Please advice.Thank you so much   

Sep 20, 2021