Primavera P6 EPPM WBS Summary Activity Type & Top-Down Estimates
Forum TopicHere's how you can employ the WBS Summary activity to list top down estimates beside bottom up estimates in http://ed.gr/dhje
Here's how you can employ the WBS Summary activity to list top down estimates beside bottom up estimates in http://ed.gr/dhje
Issue with P6 showing over allocation to things under the limit (see pic). These are multiple resources combined. Why is it showing over allocation when the resources are under the limit? Any help would be great. [[wysiwyg_imageupload:4951:]]
I m trying to review the MS schedule submitted by the Contractor, i noticed that he is changing the activity links and lags in the updated monthly schedule, does anyone have a spreadsheet or a certain method to review the links I tried exporting the ...
Hi I hope this has been posted in the right place...I have a situation where a contractor has had a clause 31 programme accepted however from day one the construction team are undertaking works in a different sequence... they clause 32 is due in 3 we...
Here's a quick tip on how to make viewable WBS charts of your schedule for presentation to stakeholders using WBS Schedule Pro and WBS Charts http://ed.gr/dj7v
How to removeasbestos yourself?
Hi, I'm trying to set up a Primavera Project for a future sensitivity/Monte Carlo analysis, therefore, I need to automatize the current schedule. I have two activities running in paralell. Activity 1 is shorter than activity two and once it fi...
When I log in as admin I can progress milestones in the spreadsheet, but when I log in as a user inside of a security group I have to progress up to 100% complete on the Gantt Chart and then change the date. The error reads that I do not have suffici...
Hi Everyone,Can anyone please help in providing solution for above Event Code in P6?The above event code occured with I was Maintaining Baseline., Could not do any further assignment. Please help. Thanks in advance.Vinit
Hi,Currently I'm preparing planned resources (machinery & manpower) required for the project in monthly frequency. However, there are two ways in assessing the planned and resources (perhaps different user different method). The method (in my opinion...
Hi All, Is it possibel to filter by trades contractor? I am currently using version 13.0.02.069 of Asta Thanks
In Primavera P6 R16.1, Primavera introduced a new column type in the lists category and here's a look at it http://ed.gr/dqcs
Hi,I was analysing a schedule for a contractor. The final milestone (constrained finish on or before) has a float of -78 days and a finish of 1 Jan 15. If I remove this constraint I was expecting the end date to move by 78 days to Middle of March. In...
Hello, If you could help me out, I'd be hugely grateful! I'm urgently trying to capture some data for my research, I have created a short survey which can be found here: http://bit.ly/2ioYgCR The survey should take no longer than 3-4 minutes, dependi...
Morning all, I've had a layout shared with me with filters built in, however I can't see how the filter works. When I go to filter it shows "custom filter" but when selected it shows no filters selected for me to interrogate. I've noticed this morn...
I'm wondering wha the best practice it for this issue. Here is a simple exampleComplete Roof (Agreed owner milestone) 1 March 2022. Constraint is "Finish On or Before".It's predesessor activity is Install Roof and Flashing. If this activity is showi...
I'm in the process of creating a Schedule which is increasingly becoming more complex with more tasks and scope being added daily, noting P6's "Go To" function allowing you to trace up and down paths of successors and predecessor paths, is there a si...
Dear ExpertsCan we use P6 for financial forecasting? Financial forecasting & planning for company's.I was asked by my boss if we could use p6 for our company's financial forecasting & planning. Please advice.Thank you so much
If the scope of an EPC project consists of 100 items, big and small, how does the planner include it in the master schedule?thanks
Hello, I want to import an Excel spreadsheet to assign a Resource ID to the same activity multiple times. P6 Professional is only assigning the respective Resource ID one time to an activity. The Max Units/Time of this resource is 16 h/d, so I should...