Search

PROBLEM WITH LEVEL 1 ROLL UP

Forum Topic

Dear Colleague,Please i have a problem with my programme with 550days duration on level 1 Roll up. After 8months of update i notice that the roll up duration on the level 1 is reduced by 7days now(543days) . I got confused because the same calender i...

Feb 17, 2016

P6’s Undiscovered Activity Change Log

Forum Topic

P6’s Undiscovered Activity Change LogDid you know that P6 has a heretofore unknown Change Log built right in the system? Yes its true!It provides schedulers and planners the ability to log any change made to an activity. And not just one! Any number ...

Feb 18, 2016

Help - Alliance planning

Forum Topic

Hi All I'm looking for some help in understanding the ramifications of the situation I am faced with:I am currently working on an alliance led project in the rail industry. There are 3 parties involved in this venture.  Us being the designe house are...

Feb 18, 2016

Help - Alliance planning

Forum Topic

Hi All I'm looking for some help in understanding the ramifications of the situation I am faced with:I am currently working on an alliance led project in the rail industry. There are 3 parties involved in this venture.  Us being the designe house are...

Feb 18, 2016

upadated programm

Forum Topic

in my upadated programm some activities are without predecessor,Sucecesssors and some activities are out of sequence,but baselene programm is Correct.so is there any problem comes or not.

Feb 18, 2016

Activity Sequence getting Changed after Adding Duration in P6

Forum Topic

Hello Everyone!! Thanks to everyone for helping by having discussion on various topics.I believe that this is the best site for the beginners and experts to learn many new things.In one of my project plan, after entering all the activities, I started...

Feb 22, 2016

Resource Help

Forum Topic

Hello,I am moving to a new company that plans to use the P6 schedule different than I am used to. The company is an Mass Grading/Sitework contractor, and plans to utilize P6 heavily for resource planning (something I don't have a huge amount of exper...

Feb 22, 2016

Resource Help

Forum Topic

Hello,I am moving to a new company that plans to use the P6 schedule different than I am used to. The company is an Mass Grading/Sitework contractor, and plans to utilize P6 heavily for resource planning (something I don't have a huge amount of exper...

Feb 22, 2016

Primavera Calendar

Forum Topic

I have always used 8hrs/day calendar but I just got a project that requires a 24/7 calendar. The way 24hrs/day calendar works in P6 really throws me offguard.In 8hrs/day calendar, work starts at 8am and ends at 5pm on the same day. The successor acti...

Feb 22, 2016

Distance Histogram

Forum Topic

While showing qunatity hisotgram along the distance scale, the graph shows double the times of actual quantity. For example, if my activity qty is 378 cum, the graph shows the cummulative qty as 756 cum. Kindly anyone help me sorting out this issue.

Feb 23, 2016

Project Cash Flow

Forum Topic

Hello Everyone,I was thinking about Cash Flow of a project. Lets consider "Buling Construction". so when doing a cash flow what items should be included.I have listed down few over here. Please let US know if anything else should also be considered.P...

Feb 23, 2016

Asta Powerproject running through Parallels on MAC

Forum Topic

HiI am trying to run my verison of Asta; 13.02, on a MAC (Pro with Retina display). Paraallels is running well with all other apps or softwares. However whilst Asta is loading and allows me to use all functionality, including BIM, the reolsution is a...

Feb 23, 2016

Scheduled and Performance % Values not displayed in the WBS

Forum Topic

Dear Planners,While analysing my project; the Scheduled % and Performance % values are not being shown in the WBS level and are only reflected for the activities. The schedule does not have any costs,resources or units assigned to it.I need to compar...

Feb 23, 2016