CONTRACT MANAGEMENT EXPEDATION V "13"

Forum Topic

Dear all; kindly not that I face an error in expedition it come into view only when importing to excel the module of Corr. Sent; a window appeared as follows:   [[wysiwyg_imageupload:957:height=182,width=350]] load_error.png   Please feedback with th...

Mar 6, 2012

Reduce the negative total float

Forum Topic

Dear Scheduler...I have project 4000 activities and with TF = -117 in the current schedule NOT baseline, because we already late and behaind the schedule. My PM he want me to reduce the -ve TF before we submit it to the owner. So, any suggestions?Tha...

Mar 6, 2012

Volume of work lag in Forensic Analysis

Forum Topic

The AACEI RP 29R-03 2011 on the modeled substractive methods provide for extraction of entire activities or a portion of the as-built durations representing delays or changes from a network analysis model representing the as-built condition of the sc...

Mar 7, 2012

Different between Oil and Construction WBS parents......

Forum Topic

Dear Schedulers,As you know for the Construction project the WBS parents (level 2) should be as below then (level 3)...1-Milestones2- Pre-Construction 3- Design4- Procurement5- Construction6- Contract CloseoutSo, how it's going to be for the Oil and ...

Mar 7, 2012

Man Hour Efficiency

Forum Topic

Friends  Please help me in the term Man hour efficiency..Please let me know the formula if any body knows... RegardsArun V

Feb 7, 2012

How to get the rollup in WBS summary?

Forum Topic

Hi Friends,               Kindly help me in the issue of generating the rollup summary in the WBS for the UserDefined fields.   Thanks & Regards Suresh KJ

Feb 7, 2012

URL Example for P6 Team Member for iPhone

Forum Topic

Hi Guys,I have P6 Optional Client and EPPM working fine on my laptop and I was trying to get the iPhone app (P6 Team Member) to connect to it. The documentation has no examples of what the URL might look like and I was hoping someone here could help ...

Feb 7, 2012

P6 Cost Allocation

Forum Topic

Hi, I am on a steep upward learning curve with P6 and need some help. My client wants all activities resourced, which I have done. He also wants a spend profile for the scheme. We are not generating our cost information at activity level, but have se...

Feb 7, 2012

Schedule % Completed to generate S Curve

Forum Topic

  Schedule % Completed to generate S Curve Hi ..there is question , I am creating an Baseline S curve ....One way is take a resource assignment spread , Cumulate this & generate s curve ...Second way I have schedule % comelete , I run schedule with d...

Feb 8, 2012

HOW UNIT % COMPLETE IS UPDATED

Forum Topic

How the unit % complete is getting updated?Even though I apply the latest duration % for each activity, the unit % is getting considerably changed only when I change the Data Date. What Data Date has to do in the updation of the Unit & completion bes...

Feb 8, 2012

How to calculate schedule slippage?

Forum Topic

Hi, One of the majore reports in Primavera is to calculate the slippage of The schedule. Can anyone help me to figure out this? Thanks

Feb 8, 2012

Student

Forum Topic

Hello everyone, I am a new member and i am a student. I am sorry if i created this topic in wrong category.I have an assignment that i have not understand it very well.I had to create a basic level WBS, Project Charter, Ganttchart, Critical Path and ...

Feb 9, 2012

Baseline has a baseline??

Forum Topic

It seems as though my baseline project has a 'memory' and is storing dates (which are visible when showing BL columns and bars) yet there is no 'secondary baseline' attached...?   Background: I was asked to rebaseline the current as-built programme d...

Feb 9, 2012