Search

Budgeted Expense Cost & Budgeted Labor Cost

Forum Topic

 Dear Experts,Could u please give some explaination on the Budgeted Expense Cost & Budgeted Labor Cost.Do we need to have budgeted labor unit when we upload the  budgeted labor cost.Please explain. Thank u so much in advance.

Sep 9, 2021

P6 Professional R19.12 Importing a WBS from Excel

Forum Topic

Hello,I would like to import a WBS from MS Excel to P6 Professional. I attempted to do this by first exporting a P6 schedule to MS Excel so make sure I have the correct format. Unfortunately, P6 Professional does not import Excel data that has a colu...

Sep 13, 2021

P6 Professional R19.12 Importing MS Excel Resource Data

Forum Topic

Hello,I have a major scheduling project with a client, and I need an efficient way to input Resource data into P6 Professional. I would like to have the client provide a Microsoft Excel Spreadsheet of resource data and then import this into P6 Profes...

Sep 15, 2021

WBS Summary activity VS LOE activity

Forum Topic

Hi,There are sometimes in our projects that we use LOE to put the cost for a WBS with some activities ( Because of an internal agreement) I wanted to know which one is better and why? ( LOE or WBS Summary)

Feb 4, 2023

Primavera P6 Create Activity Codes

Forum Topic

Hello Guys, i have more than 300 zones, districts and sublines, in Primavera yes i can write manually all lines to activity code menu, but it takes much time, is there a any easy way to create activit codes then import Primavera, i am not asking assi...

Feb 5, 2023

Show/calculate elapsed days between two tasks.

Forum Topic

Is it possible for ASTA to count the total number of days between two tasks? IE, I have an 'implement detour' and a 'remove detour' task at the beginning and end of my project respectiely, with tasks in between, and I need to know how many days the d...

Feb 7, 2023

Different setups for Primavera Professional

Forum Topic

P6 Professional, not EPPM which is a different can of worms..1. on your system - if you have a serial number, can't you just keep paying the "maint. fee" and then keep getting updates for free - isn't this the best way to go?.2. through citrix or sim...

Feb 8, 2023

Scheduling Challenges in Agile & Distributed Projects

Forum Topic

Our paper looking at the scheduling challenges in agile and distributed projects has been published in the February 2003 edition of PM World Journal: https://pmworldjournal.com/Critical path theory is based on an assumption that to deliver a project ...

Feb 11, 2023

Monte Carlo Simulation Challenges

Forum Topic

Risk simulation is becoming popular but most risk simulation tools and the ways how they are used miss some important functionalities that make the results of this simulation unreliable.I am continuing my posts about 'Monte Carlo Simulation Challenge...

Feb 16, 2023