Primavera P6 Professional Reporting
Forum TopicHere's a quick primer on how to generate a tabulated report of schedule progress in Primavera P6 Professional http://ow.ly/JRLv30aWEZa
Here's a quick primer on how to generate a tabulated report of schedule progress in Primavera P6 Professional http://ow.ly/JRLv30aWEZa
I have equipment procurement activities that need to be delivered just in time for each install. I place all the orders on Day 2 of the project. I want to show, for each equipment, a lead time extending upto its install activity (its successor) sta...
Hi Everyone, For us www.planningplanet.com very good to discuss each and every topics as well as doubt also. Same like this forum,kindly request me other forum. It may helpful to everyone guys. Thanks,Vasanth
Primavera P6 Professional has the functionality to both export and import XML files. The question is what exactly is the XML data format? Here we answer that question http://ow.ly/f45p30aYPoS
All,I'm organizing the layout using activity code, all the activity names are using English, and at the right side of the bar, I'm showing the bar label use another language to translate the activity names, so the people didn't know English can read ...
I have been previously running 8.2 using progress overide on the programme. Occasionaly I have inadvertantly added logic that created a loop that was detected and removed from the programme. Otherwise the scheduling wont run.This month we upgraded to...
I have a very strange problem with many aspects, I will illustrate it at the following points : 1. this problem occurs with many project not only one and at different PCs2. When copying an Assigned baseline from inside a project from the maintain ba...
a
It may seem like a minor point, but I discovered that adjusting the task table row height in Microsoft Project schedules is not readily apparent. Here's how you do it http://ow.ly/pkrq30b35Sb
I am trying to import a line, list IDs and Activity name is all i really need. In 16.2 it is giving me this error message....The User Preferences used to create this Excel file are not the same as your current preferences. Importing this file could c...
Hello, I am an Undergrad student and i am asked to do :A preliminary schedule utilizing primavera software for a commercial two story with one basement building. The following is the general description: 1- The building is concrete/structural steel ...
Hi, According to many risks can either have a negative outcome or a positive outcome. So if a risk has a positive outcome why is it considered as a risk and not as an opportunity? I realize that positive thinking says that look at all the risks...
Dear All,I urgently need your help if you can share with me a sample Schedule for Hydro-Electric power plant. Kindly email it to [email protected] Thank you all .Best Regards.
Greeting,Any one could please help to update CEUs for PSP.It looks unclear to me. if any one have done , i like to get his experience in mentioned subject.
Hi,I am Pranav Patil, recently I have faced one interview. They asked me to calculate manpower required for a building RCC work whereas building has 4000 Sqm built up area for each floor. Total floors are 30 Nos. Scheduled completion is 15 Month.I ca...
The .xls SDK files downloaded from oracle support is not working in a 64 bit OS/Office.Its giving an error to update the VB coding to 64 bit(The oracle file created in a 32 bit OS).Is there anyone updated the codes to 64 bit ? or from where can i get...
Dear All,I got P6 re-installed on my system as the oracle database crashed, now i am working with SQL server. After the new installation i am not able to print profile which was earlier available in the print preview options. Please advise.[[wysiwyg_...
Hi everybody.This is my first input to planningplanet. Sorry if it was answered in the past. I coudnt find anything about it. The point is that the projects I usually hande have more than 65000 relatioships. I use P6 version 15.1 and the only export ...
Hi all,I've made several filters within a P6 schedule to show certain WBS sections, and FOW assigned codes.I know how to save the layout, export layout and import again to transfer filters between schedules. For some reason however, P6 doesn't want t...
Dear all,I'm new to P6, trying to run installation in my destop. I find it difficult proceeding when i got to DATBASE CONFIGURATION.WHAT DO I DO NEXT?