Update material resource units

Forum Topic

Hello everyone,I am trying to update my actual blockwork quantites in p6. My activity type is physical % complete. I have physical % complete values. I manually enter all these values to units %complete in the activity details resource field. I want ...

Feb 3, 2017

Best Practice For Assigning Formwork resource

Forum Topic

what is the best practice to assign Form work resource in p6, i assign as material and fill in the budget units / time, but hthe issue is using budget units/time when tracking by month read the Qty. of formwork Muliplied by the duration for every ass...

Feb 4, 2017

Creating WBS in MSP

Forum Topic

Can anybody help me in creating WBS for it.1.queplumbing, common results for plumbing, schedule of piping, meter and gauges, schedule for piping and pumps, schedule for fixtures, domestic water piping, booster pumps, water distribution, general duty ...

Feb 5, 2017

Budget distribution in Recovery Programme

Forum Topic

HI,I made a recovery programme, developed from the latest update of the approved baseline programme. Budget is loaded in the programme. In the activity spreadsheet of the recovery schedule, the budget seems to be distributed not as per the dates. Man...

Feb 5, 2017

Safety Rules

Forum Topic

We are having some work done at our house and a young labourer was engaged in cutting bricks into headers with an angle grinder. My wife called out "Peter - where are your safety goggles?" Peter "In my toolbox" Wife "Well put them on or I'll slap you...

Feb 6, 2017

How do you insert weather delay allowance into a new schedule

Forum Topic

Hello,When you are preparing a baseline in the beginning, what is your practice to insert the anticipated weather or miscellaneous delays into a schedule?You put lags? if so where?You put an overall delay item in the end and decreases it as delays oc...

Feb 6, 2017

Paste Linking

Forum Topic

Hi all Can anyone please help me out and give me some guidance. I would like to set up a task pool that could be linked to the main programme I.e. If I was to alter the the task pool durations or operation it would automatically alter the main progra...

Feb 7, 2017

Primavera P6 EPPM Defining Baselines

Forum Topic

Here's how to display a project baseline and primary user's user baseline on the Gantt chart in Primavera P6 EPPM http://ow.ly/o3Ts308NScH

Feb 8, 2017

PDF writer not filling print area from P6

Forum Topic

Hi all,I am trying to create some PDF prints of a programme from P6 16.2 and when setting up a print for A3 and printing via pdf writer (i have tried Microsoft to PDF, CutePDF Writer and DORO) the writer is not filling the print area. When in the pri...

Feb 8, 2017

Critical Path Not Showing on P6 Schedule

Forum Topic

I am currently preparing a project schedule for a client. Project spec says: (1)  Schedule must show critical path. (2) Critical path should be defined as the "Longest Path" (3) Last activity (Project Finish Milestone) must have a "Finish On" constra...

Feb 8, 2017

Primavera Duration Types

Forum Topic

Hi all, could someone please explain with scenario/examples different duration types in P6. I am struggling to understand when to use what I.e fixed duration & units, fixed united etc. Appreciate your anticipated help, thanks

Feb 10, 2017

In-Browser Project Scheduling

Forum Topic

Simply download and install anything by the help of project scheduling features of project management software. Critical path schedules and resource allocation are the main resources of the software that highlight suggested activities in the section....

Feb 10, 2017

In-Browser Project Scheduling

Forum Topic

Simply download and install anything by the help of project scheduling features of project management software. Critical path schedules and resource allocation are the main resources of the software that highlight suggested activities in the section....

Feb 10, 2017

Tracking Welds Per Inches and Piping in P6 8.3

Forum Topic

Iam working on a Project where they want to track welds per inches and Piping in P6 8.3. They also want earned value regarding this. What is the best way to set that up in P6 to track accurately?    Thank You in Advance!!!!!!!!!!!!!!

Feb 11, 2017

Gantt chart and resource allocation

Forum Topic

Hi!The customer requests a layout/view with the gantt chart for the coming month and the resource allocation beneath. (The resources in this case is machinery.) I could almost manage to do this by having the "normal" gantt chart on the upper part of ...

Feb 13, 2017

Gantt chart and resource allocation

Forum Topic

Hi!The customer requests a layout/view with the gantt chart for the coming month and the resource allocation beneath. (The resources in this case is machinery.) I could almost manage to do this by having the "normal" gantt chart on the upper part of ...

Feb 13, 2017

P6 - Different colours on different projects in stacked histogram

Forum Topic

Hi,I have different projects in Primavera, which make use of the same resources. I want to show the projects in an histogram, with each project a different colour. Does anybody know if this is possible?In the 'stacked histogram' of resource usage pro...

Feb 13, 2017

Line of Balance

Forum Topic

Hi all I am seeing more and more people wanting a line of balance set up as a spreadsheet, with each plot (housing project) down the left side and each activity along the top with the duration of each task identified, and then in each meeting cell a ...

Feb 14, 2017