Monitoring Deadline Dates in Primavera P6 Professional
Forum TopicHere's a great tip on how you can display Deadline Dates on the Gantt Chart in Primavera P6 Professional http://ow.ly/KFH63069fas
Here's a great tip on how you can display Deadline Dates on the Gantt Chart in Primavera P6 Professional http://ow.ly/KFH63069fas
http://www.mpug.com/articles/run-microsoft-project-on-a-mac/
Hi, I've allocated income value of £1m to a line in a project, then I've allocated income value of £2m to another line in a project, (same programme) and allocated a likelihood of 50% likelihood to both projects. Is there a way of getting the income ...
Hello,I'm currently developing a BIM type software and I would like to export the BOQ (with quantities, resources,etc.) in Spider.It can be done very easily using .txt files and then imported in Spider but I was wondering if the .txt files can be com...
Hi,I upgraded our SQL server database for Primavera from v7 to 16R2. No problem connecting to the database from Management Studio.Installed P6 Professional R16.2-64bit on my laptop Win 7 OS. When I tried to configure database connection, I got a Ru...
I am testing Primavera P6 as a user. My company is migrating our existing server to loadspring to see the impact of change. Is anyone has the checklist, so i coud test these areas so nothing is missed out. Thanks
I am testing Primavera P6 as a user. My company is migrating our existing server to loadspring to see the impact of change. Is anyone has the checklist, so i coud test these areas so nothing is missed out. Thanks
Hello Everyone!First off, I appreciate you taking the time to read this thread. I've recently joined a new company. My background is mostly in enterprise sales and small scale project management (team of 3 on less sophisticated business). I was lucky...
Hi Planners,How to define the KPIs for design works?Regards,Muataz
Hi FolksIm importing same xer file into enterprise and into standalone version of p6Im getting different dates&floats when scheduling with retained logic when investigating reason, i saw that at completion durations are different for some in-progress...
Since Primavera released P6 R8.4 back in October of 2014, a standalone installation of P6 Professional can use a small, simple, SQLite database. Here's how to do it http://ow.ly/Y9nj306j5dV
Hi Planners,Suppose I have 4 days duration activity and the status date is at the end of the second day, the % complete is 75%, this means that only one day remaining which is clear but the bar does not reflect this because the % complete is linked t...
Having emailed 150 copies of a Typical Project Planning Procedure to PP members at their request I thought that I might raise the subject of the quality of the planning work we are all busy producing. How do we assure/assess our work? A lot of recent...
Here's how to tweak the Primavera P6 Professional cure time task approach to retain a continuous ‘longest path’ in support of schedule optimization http://ow.ly/fHoK306nl5P
Hello all,I´d like to perform a What If scenario for my managers where we could see the possible reduction in our schedule by using Overtime, and second shifts, and also show the Cost Impact of this decision in order to see if this is a good option f...
Hello Everyone, Can anyone provide me the activity details for Clarifier Inspection and Repair Project as urgent. I’ll be oblized to get any feed back. Any additional guidelines or job knowledge also will highly help me. Regards, Sharique
When I Import my Cost Loaded Schedule from One Computer to another the Cost from Project Reduces..Cost for Many activities goes missing.But the main computer in which the Cost Loading was done, If I import it again on the same computer Cost comes cor...
Hey All,I've worked with various Schedule Analytics tools in the past but I feel that some functionality and capabilities are missing. I'm on a Schedule Analytics Software Research mission to find [or develop] a good Scheduling Analytics Software.So...
Hey All,I've worked with various Schedule Analytics tools in the past but I feel that some functionality and capabilities are missing. I'm on a Schedule Analytics Software Research mission to find [or develop] a good Scheduling Analytics Software.So...
Im Trying to print, either to printer or preferrably adobe pdf file. i have multiple activities that were suspended due to delays and i need to print the schedule and display those areas of suspension (where it is bottle necked) i see them in my gant...