Dassian?
Forum TopicDoes anyone have any experience of the Dassian EVM tool please?
Does anyone have any experience of the Dassian EVM tool please?
Hello everyone , any body has an information about Planning ( Time schedule and Cost estimation ) for Green Buildings ??and what the effect of Green on the Plan I mean >> If there are two buildings that are same in the Structural and Architectural de...
i have one project with baseline & update with percent complete as Physical. I was showing the project progress as Schedule % complete VS performance % complete.Now i have changed the percent complete as duration.please tell me how to show the proje...
Primavera P6 Projects may be assigned one of four states: Active, Inactive, Planned, and What-if. These states are useful for generating reports on the entire portfolio of projects.This article looks at each of these http://ow.ly/4mW8DE
We currently have P6 Professional R8.3.2 installed on a terminal server running Windows Server 2008 R2 Datacenter. I am having issues when trying to copy and paste text using the right click. I am able to right click on activities, projects, and wb...
Hello everyone,this is my first post on this forum but I've been coming here for years when I was looking for some answers. I've been using the search tool but as I couldn't find anything I thought I would ask your opinion.Normally when I create an a...
Hi, trying to do a college assignment and mid way through programme, when I enter 1d for a duration it jumps to 6000w. Has anybody had a similar issue or know what setting will rectify this. Thanks
I am working as an Engineer for a Building Project.Our Contractor has failed to complete the Works within the Contractual Time for Completion. The delays are solely attributed to the contractor. Now, we would like to receive from the Contractor, hi...
I have a level of effort activity with duration % complete. Cost is assigned to it as material resources price. But the cost is not getting distributed through the duration of the activity. In the profile/spreadsheet, the cost just stays in the start...
Hi all,there is any method to link maximo with p6. in other words in the companies who are using maximo what the best method to integate the work otherwis there will adouble work and seprate islands in both sotwares.Anyone please can inform the opt...
hey everyone,Actually i am trying to create planning and schedulling for construction of dam using ms project.can somebody upload any sample ms project file for construction of dam
Dear All, Introduction:We are preparing for a revised program (Rev.2), the baseline program (Rev.1) already having in-progress activities and will be considered as a baseline for Rev.2 program. The planned dates and planned values to be calculated f...
Hi Friends,My issue is i am getting wrong Critical Paths & i know it is wrong.How can i tackle it.Links are properly connected.Please give the solution. Regards, Vigeeth
Dear Primavera wizards,I am having an issue exporting version 15 to Microsoft Project. Normally, in previous versions, I seem to recall exporting to .mpp files. This version only gives me the option of .xml's (2010, 2007, 2002/2003) and MPX. This ...
Can a P6 Pro (PPM license) be used to connect to EPPM database? Will that break the license agreement? We Currntly have PPM license and we want to start buying EPPM going forward. EPPM wont connect to PPM database but PPM can connect to EPPM database...
HelloI have an issue with the function Check Schedule. It does work for projects up to 1500 activities but not if there are more activities.Is there any setting within the web server which limits the size of a file? Do you know any other reason?I'm u...
Here a great tip on how to use curtains in Microsoft Project to show what work is being done within a Sprint http://ow.ly/4n4SOv
Hello, Can anyone please send me the sample PMS in MS-Excel format, because i am not having primavera software. mail me to: [email protected]
I am doing an update for which one activity needs to finish on May 2nd and its saying remain finish cannot be earlier than remain start. Remain start is May 17 and I manually tried to change it but it's going back to May 17. What to do. Please help n...
One of the first steps in planning a project is to break down the project by its major deliverables, i.e. the product or service components. An organized hierarchical break down or decomposition of all the deliverables is known as the Work Breakdown ...