Waterproofing

Wiki Page

Task / DescriptionSlow  Ave  Fast   Units Asphalt coatings, horizontal surfaces3.5 4.2 5.8  m2/hr Asphalt coatings, vertical surfaces1.2 1.7 2.2  m2/hr Bituminous Brushed application, 2 coats4.8 5.0 6.3  m2/hr Bituminous Brushed application, 3 coats3...

Jul 14, 2011

Trackwork

Wiki Page

Trackwork...Task / DescriptionSlow  Ave  Fast   Units FST Floating Track Slab, side restraints9.6 -  -   m/day FST Floating Track Slab, resin pads10.2 -  -   m/day FST Floating Track Slab, slab units10.6 -  -   m/day PCBT - Pre-cast Concrete Block Tr...

Jul 14, 2011

Tower Cranes

Wiki Page

Tower Cranes...Task / DescriptionSlow  Ave  Fast   Units Erect and Setup 50m gib-  11.0 7.5  days Dismantle 50m gib-  10.0 -   days Lifting, Reinforcement Bins and Cages, 1st 15m lift-  3.2 -   mins/lift Lifting, Reinforcement Bins and Cages, above 1...

Jul 14, 2011

Steel Strutting

Wiki Page

Steel Strutting...Task / DescriptionSlow  Ave  Fast   Units Horizontal heavy duty strutting-  2.0 -   days/no Diagonal heavy duty strutting-  6.0 -   days/no

Jul 14, 2011

Soil Mix Walls

Wiki Page

Soil Mix Walls...Task / DescriptionSlow  Ave  Fast   Units Three Auger Drill, cement and cure3.8 4.5 6.4  m/day

Jul 14, 2011

Sheeted Roofs

Wiki Page

Sheeted RoofsTask / DescriptionSlow  Ave  Fast   Units PVC Sheeted Roofs, large areas-  50.0 -   m2/day PVC Sheeted Roofs, small areas-  40.0 -   m2/day Plastic Profiled Sheet Systems-  54.0 -   m2/day

Jul 14, 2011

Secant Piling

Wiki Page

Secant Piling...Task / DescriptionSlow  Ave  Fast   Units Construct 30m dia cofferdam, 255 piles/concrete base-  12.0 -   wks

Jul 14, 2011

Rule of Thumb

Wiki Page

Rule of ThumbTask / DescriptionSlow  Ave  Fast   Units Site Investigation Pre Drilling5.0 4.0 3.0  days/no Ground Excavation, Hydraulic Backhoe-  50.0 -   m3/day Bored Piling, 25-70m deep10.0 8.0 6.0  days/no Formwork Fixing-  12.0 -   m2/day Reinfor...

Jul 14, 2011

Restoration Works

Wiki Page

Restoration WorksTask / DescriptionSlow  Ave  Fast   Units Façade Cleaning, Water Jetting-  25.0 -   m2/day Façade Cleaning, Acid Etching-  9.0 -   m2/day Façade Cleaning, Grit Blasting-  12.0 -   m2/day Cladding Restoration, Brickwork-  6.5 -   m2/d...

Jul 14, 2011

Rendering

Wiki Page

RenderingTask / DescriptionSlow  Ave  Fast   Units Large Wall Areas, applied in 2 coats-  2.2 2.7  m2/hr Small Wall Areas, applied in 2 coats-  1.5 1.7  m2/hr Narrow Widths, applied in 2 coats-  1.2 1.4  m2/hr Columns and Beams, applied in 2 coats-  ...

Jul 14, 2011

Reinforcement Ratios

Wiki Page

Reinforcement RatiosTask / DescriptionSlow  Ave  Fast   Units Pile Cap, Concrete m3 x Ratio = Rebar Tonnes-  14.8 -   % ratio Base Slab, Concrete m3 x Ratio = Rebar Tonnes-  13.2 14.1  % ratio Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes-  20.6...

Jul 14, 2011

Transportation Power Supply

Wiki Page

Power SupplyTask / DescriptionSlow  Ave  Fast   Units AC Install 2 no Service transformers, 6 men-  12.0 -   days AC Install 2 no Switchgear, 7 men-  12.0 -   days AC Install Associated Trays and ladders, 3 men11.0 5.0 -   days AC Cable Terminations ...

Jul 14, 2011

Plasterboard

Wiki Page

PlasterboardTask / DescriptionSlow  Ave  Fast   Units Boarding to Plaster dabs3.6 4.0 5.5  m2/hr Boarding to Stud-work/Metal Lathes4.0 5.0 6.7  m2/hr Boarding 12mm nailed to studding-  12.5 -   m2/hr Boarding 19mm nailed to studding-  16.5 -   m2/hr ...

Jul 14, 2011

Partitioning

Wiki Page

PartitioningTask / DescriptionSlow  Ave  Fast   Units Timber Studding5.9 6.2 6.8  m/hr Metalwork System (MF) Studding1.6 2.0 2.5  m2/hr Tape, Joint Sand and Top Coat Plasterboard1.1 1.5 2.1  m2/hr Skimming to Plasterboards5.5 6.1 6.7  m2/hr 5mm Hardb...

Jul 14, 2011

Drainage, Manholes and Gulleys

Wiki Page

Manholes and GulleysTask / DescriptionSlow  Ave  Fast   Units Concrete Pre-Cast Manhole Units, 610 x 455 x 51 mm-  1.2 -   hrs/no Concrete Pre-Cast Manhole Units, 990 x 610 x 64 mm-  1.6 -   hrs/no Brickwork Manhole, 1.0 brick engineering-  0.3 -   m...

Jul 14, 2011

Kerbs & Paving

Wiki Page

Kerbs & PavingTask / DescriptionSlow  Ave  Fast   Units Concrete Slabs, laid on bedding, to slight falls2.7 -  4.2  m2/hr Concrete Slabs, laid on bedding, to steep falls2.3 -  2.7  m2/hr Concrete Slabs, laid in mortar, to slight falls1.5 -  2.3  m2/h...

Jul 15, 2011

Formwork

Wiki Page

FormworkTask / DescriptionSlow  Ave  Fast   Units Pilecaps, < 0.7m20.9 1.6 2.0  m2/hr Pilecaps, 0.7-2.5m21.6 2.0 2.3  m2/hr Pilecaps, 2.5-3.0m22.0 2.3 2.5  m2/hr Pilecaps, > 3.0m22.3 2.5 3.1  m2/hr Ground Beams, < 0.7m21.1 1.7 1.8  m2/hr Ground Beams...

Jul 15, 2011

Floor Finishes

Wiki Page

Floor FinishesTask / DescriptionSlow  Ave  Fast   Units Granolithic Flooring-  3.1 -   m2/hr Terrazzo Flooring, in-situ-  3.6 -   m2/hr Terrazzo Flooring, pre-cast-  4.6 5.1  m2/hr Mosaic Tiling, 0.045x0.045m-  1.5 2.2  m2/hr Clay, quarry Tiles, smal...

Jul 15, 2011

Fencing Works

Wiki Page

Fencing WorksTask / DescriptionSlow  Ave  Fast   Units Site Hoarding, timber posts, plywood nailed to horizontal rails1.0 1.2 -   m/hr Post Erection, Timber / Metal, dig, erect, fix3.3 4.5 -   no/hr Post Erection, Concrete, dig, erect, fix3.2 4.0 -  ...

Jul 15, 2011

Electrical System

Wiki Page

Electrical SystemTask / DescriptionSlow  Ave  Fast   Units Railway Station 1st Fix-  38.0 -   wks Railway Station 2nd Fix-  16.0 -   wks Railway Station T&C-  8.0 -   wks Cable Installation, 1 cable laid in trench and protect-  6.2 -   m/hr Cable Ins...

Jul 15, 2011