Drainage, Manholes and Gulleys

Wiki Page

Manholes and GulleysTask / DescriptionSlow  Ave  Fast   Units Concrete Pre-Cast Manhole Units, 610 x 455 x 51 mm-  1.2 -   hrs/no Concrete Pre-Cast Manhole Units, 990 x 610 x 64 mm-  1.6 -   hrs/no Brickwork Manhole, 1.0 brick engineering-  0.3 -   m...

Jul 14, 2011

Kerbs & Paving

Wiki Page

Kerbs & PavingTask / DescriptionSlow  Ave  Fast   Units Concrete Slabs, laid on bedding, to slight falls2.7 -  4.2  m2/hr Concrete Slabs, laid on bedding, to steep falls2.3 -  2.7  m2/hr Concrete Slabs, laid in mortar, to slight falls1.5 -  2.3  m2/h...

Jul 15, 2011

Formwork

Wiki Page

FormworkTask / DescriptionSlow  Ave  Fast   Units Pilecaps, < 0.7m20.9 1.6 2.0  m2/hr Pilecaps, 0.7-2.5m21.6 2.0 2.3  m2/hr Pilecaps, 2.5-3.0m22.0 2.3 2.5  m2/hr Pilecaps, > 3.0m22.3 2.5 3.1  m2/hr Ground Beams, < 0.7m21.1 1.7 1.8  m2/hr Ground Beams...

Jul 15, 2011

Floor Finishes

Wiki Page

Floor FinishesTask / DescriptionSlow  Ave  Fast   Units Granolithic Flooring-  3.1 -   m2/hr Terrazzo Flooring, in-situ-  3.6 -   m2/hr Terrazzo Flooring, pre-cast-  4.6 5.1  m2/hr Mosaic Tiling, 0.045x0.045m-  1.5 2.2  m2/hr Clay, quarry Tiles, smal...

Jul 15, 2011

Fencing Works

Wiki Page

Fencing WorksTask / DescriptionSlow  Ave  Fast   Units Site Hoarding, timber posts, plywood nailed to horizontal rails1.0 1.2 -   m/hr Post Erection, Timber / Metal, dig, erect, fix3.3 4.5 -   no/hr Post Erection, Concrete, dig, erect, fix3.2 4.0 -  ...

Jul 15, 2011

Electrical System

Wiki Page

Electrical SystemTask / DescriptionSlow  Ave  Fast   Units Railway Station 1st Fix-  38.0 -   wks Railway Station 2nd Fix-  16.0 -   wks Railway Station T&C-  8.0 -   wks Cable Installation, 1 cable laid in trench and protect-  6.2 -   m/hr Cable Ins...

Jul 15, 2011

Professional Development for Project Controls

Wiki Page

Professioanl development for projects controls specailists is a tricky areas with very little on offer. Project managers seem to have a wide range of choice including PRINCE2 and APMP in the UK and PMP Certification for those in the international mar...

Jul 15, 2011

Decking

Wiki Page

DeckingTask / DescriptionSlow  Ave  Fast   Units Simple Universal Beam Steel Bridge, concrete bridge deck, grano cover-  7.1 -   m/day

Jul 19, 2011

Excavate and Remove

Wiki Page

 Excavate and RemoveTask / DescriptionSlow  Ave  Fast   Units Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil14.5 20.0 25.6  m3/hr Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds15.2 20.4 25.6  m3/hr Excavate Spoil Heaps to Tr...

Oct 14, 2010

Termination of the Contract

Wiki Page

Termination of the contract For termination of a contract due to default by the Contractor, FIDIC 4th Edition provides remedies for the employer in Clause 63.1 which, save for a fairly common provision relating to the contractor’s bankruptcy, liquida...

Oct 18, 2010

Objectives of an International Guild

Page

We have collated here, the feedback and 'objective-statements' of the community.  This is by no means a definitive list but provides a concise viewpoint of the feedback of the planners and employers to date.To show and demonstrate acknowledgement of ...

Oct 19, 2010

Partner Benefits

Page

Planning Planet Partners – the community has a Partner directory http://www.planningplanet.com/partners and each Partner is provided with a Partner Group.Partner Group - members of the PP Community can join the Partner Group as members and the Partne...

Oct 20, 2010

Virtual Summit 2010

Page

[[wysiwyg_imageupload:107:]]Did you attend the Online Oracle Virtual Summit?  If so, or even if you didn't, do let us know your thoughts and feedback; Good or Bad via [email protected]  Be Proud of your Planning

Oct 28, 2010

Concrete Finishing

Wiki Page

Concrete FinishingTask / DescriptionSlow  Ave  Fast   Units Surface Finishing, Steel Float By Hand9.2 13.9 25.0  m2/hr Surface Finishing, Wood Float By Hand11.7 17.2 29.4  m2/hr Surface Finishing, Power Float13.9 20.8 37.0  m2/hr Surface Finishing, L...

Jul 19, 2011

Ceiling Finishes

Wiki Page

Ceiling FinishesTask / DescriptionSlow  Ave  Fast   Units Suspended Ceilings, office situations-  2.6 3.5  m2/hr Suspended Ceilings, First Fix-  0.7 -   m2/hr Suspended Ceilings, Second Fix-  1.2 -   m2/hr

Jul 19, 2011

Carpentry Final Fixing

Wiki Page

Carpentry Final FixingTask / DescriptionSlow  Ave  Fast   Units Windows, Softwood, 3.0-7.0m20.6 0.4 0.3  hrs/no Windows, Softwood, 7.0-10.0m21.3 0.9 0.6  hrs/no Windows, Hardwood, 1.0-3.0m20.4 0.3 -   hrs/no Windows, Hardwood, 3.0-7.0m20.7 0.5 0.4  h...

Jul 19, 2011

Carpentry Carcassing

Wiki Page

Carpentry CarcassingTask / DescriptionSlow  Ave  Fast   Units Windows, Timber Frames for Bricklaying1.1 0.5 0.1  hrs/no Windows, Drill, Screw & Plug extra over0.3 0.1 -   hrs/no Door Frames, Softwood, 1.0-3.0m2-  0.2 -   hrs/no Door Frames, Softwood,...

Jul 19, 2011

Carpentry & Joinery

Wiki Page

Carpentry & JoineryTask / DescriptionSlow  Ave  Fast   Units Formwork to Soffit of Manhole-  1.8 -   m2/hr Formwork to Walls of Manhole11.2 14.2 20.2  m2/hr Formwork to Road Edges, straight-  7.7 -   m/hr Formwork to Road Edges, curves-  6.2 -   m/hr

Jul 19, 2011