Slate Roofs
Wiki PageSlate Roofs Usually carried out with a 2 man gang, sometimes with an additional labourer. Natural Welsh Slate 3.5-5 mm thick 18.0 m2/day Natural Cumbrian 8-11 mm thick 8.5 m2/day Asbestos Slates 36.0 m2/day
Slate Roofs Usually carried out with a 2 man gang, sometimes with an additional labourer. Natural Welsh Slate 3.5-5 mm thick 18.0 m2/day Natural Cumbrian 8-11 mm thick 8.5 m2/day Asbestos Slates 36.0 m2/day
Usually carried out with a 2 man gang with 1 labourer. The rates include for felting, battening and fixing of tiles etc. Concrete Interlocking Tiles 52 m2/day Clay Pan Tiles 26 m2/day
Asbestos Type Roofs A typical rate of 39 m2/day
Asphalt Roofs Usually carried out with a 2 man gang with an additional 1 or 2 labourers. A typical composite rate of 45 m2/day
Built-Up Felt Roofs Usually carried out with a minimum of a 1 man gang with a labourer. Large Roof Areas = 52 m2/day Smaller or Complicated Areas = 35 m2/day
Metal Decking SystemsUsually carried out with a minimum of a 3 man gang with a labourer.Large Roof Areas = 70 m2/daySmaller or Complicated Areas = 28 m2/dayMetal DeckingTask / DescriptionSlow Ave Fast Units Metal Decking, large areas- 70.0 - m...
Profiled Sheeting Systems Usually carried out with a minimum of a 2 man gang. Large Roof Areas = 54 m2/day
P.V.C. Sheeting Usually carried out with a minimum of a 3 man gang with a labourer. Large Roof Areas = 50 m2/day Smaller Areas = 40 m2/day
Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Lead Roofing Flat Roof Lead Work = 2.5 m2/day Sloping Roof Lead Work = 2.1 m2/day
Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Copper Roofing Flat Roof Copper Work = 3.0 m2/day Sloping Roof Copper Work = 2.7 m2/day
Zinc Roofing Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Flat Roof Zinc Work = 2.3 m2/day Sloping Roof Zinc Work = 1.9 m2/day
Aluminium Roofing Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Flat Roof Aluminium Work = 2.8 m2/day Sloping Roof Aluminium Work = 1.9 m2/day
Titanium Roofing System Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Titanium roof on multiple sub‑layers. Typical composite rate of 9.5 m2/day. Inst...
Metal Roof Features Composite rates have been calculated to provide an approximation of the time elements for these ancillary parts to metal roofs. Dormer Cheeks 1.36 m2/day Flat Gutter & Coping Flashings negligible time Step Gutter & Shaped Copings ...
DownPipes 75 mm UPVC Pipes 3.3 m/hr 75 mm Cast Iron Pipes 2.1 m/hr 72 mm Aluminium Pipe System 2.5 m/hr Guttering 75 mm UPVC Gutter 3.1 m/hr 75 mm Cast Iron Gutter 2.5 m/hr 72 mm Aluminium Gutter System 2.9 m/hr Fittin...
Roof Protections Gravel & Chippings - Allow a rate of 1.4 tonnes/day for transporting and laying out solar reflective chippings.
Definition of Building Services - First Fix Environmental Control Systems This shall include the installation of all ECS equipment such as MCC's, fans and AHU's. In addition the installation of all primary and secondary ductwork and pipework sys...
Definition of Building Services - Second Fix Environmental Control Systems This shall include the installation of fan coils, EP panels and PLC panels. In addition, the insulation of all primary and secondary ductwork as well as pipework systems; leak...
Lift InstallationSequence of WorkA standard installation sequence for a "conventional hydraulic lift with 2 - 3 storeys and doors etc.Handover of lift shaft structure and associated lift machine room.Deliver all materials to site, 2 weeks.Hoisting o...
Installation SequencesIndustrial and Commercial installations usually commence when false ceilings, floorings and final decorations are substantially complete. Kitchen Hood Installations are done before false ceiling completion and kitchen equipment ...