Trench Excavations

Wiki Page

Trench Excavation...Task / DescriptionSlow  Ave  Fast   Units Hydraulic Excavator, 0.3m3 bucket, Sand/Soil5.6 7.1 8.2  m3/hr Hydraulic Excavator, 0.3m3 bucket, Gravel Beds4.8 6.1 7.3  m3/hr Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk4.8 6.1 7.1  m3...

Mar 1, 2009

Linear Planning

Wiki Page

Linear Planning is [[planning]] or scheduling of project management tasks where distance is a significant factor in the project. Examples of projects include roads, rail, pipeline and transmission lines. Linear planning considers not only the time fa...

Mar 2, 2009

Underpinning

Wiki Page

Concrete Pinning - During underpinning operations a cycle of every 4th or 5th pin being constructed concurrently is adopted.Rate of 1.2 m/day, i.e. 1 number support pin per dayUnderpinning...Task / DescriptionSlow  Ave  Fast   Units Concrete Pinning,...

Mar 1, 2009

Barrette Piles

Wiki Page

Barrette PilesTask / DescriptionSlow  Ave  Fast   Units Rule of Thumb, overall rate by Mill0.5 1.1 1.2  hrs/no Fabricate reinforcement cages-  4.0 -   hrs/cage Concreting barrette panels40.0 50.0 55.0  m3/hr Trimming top of barrette panels-  2.4 -   ...

Mar 1, 2009

Structural Steelwork

Wiki Page

Steel FramesTask / DescriptionSlow  Ave  Fast   Units Steel Frame and Roof Members3.4 -  4.6  Tons/day Wall Frame, Bow String Truss and Frame-  1.6 -   Tons/day Roof Frame, Curved Truss and Frame-  5.2 -   Tons/day Wall Frame, Glazed Frame and Atrium...