Hand Dug Caissons

Wiki Page

Principles Of Construction  This type of "pile wall" is typical employed in areas where headroom or proximity to buildings restricts the use of large diameter bored pile drilling rigs, or where the wall is to be located very close to an existing stru...

Feb 22, 2009

Cable Car

Wiki Page

The 21 months duration for the 14km cable car project from the land available date is made up of the following activities:5 months lead time to the mast foundation contract before the cable car contractor can get access to the foundation for a 10 mon...

Feb 22, 2009

Cutting Holes

Wiki Page

Cutting Holes in concrete by Hand (no/hr Hole depth (mm) --> 0-75 75-125 125-250 250-375 375-500 Ne 50 cm2 2.94 1.85 1.75  -   - 50-100 cm2 2.22 1.39 1.32  -   - 100-150 cm2 1.67 1.11 1.05  -   - 250-500 cm2 1.28 0.88 0.83  -   - Cutting Holes in con...

Feb 28, 2009

Brickwork

Wiki Page

Output 25m2 per man week overall facing brickwork

Mar 1, 2009

Plastering

Wiki Page

PlasteringTask / DescriptionSlow  Ave  Fast   Units Browning (undercoat), Internal Walls under 2.5m high2.2 2.8 3.1  m2/hr Browning (undercoat), Internal Walls over 2.5m high2.1 2.6 2.8  m2/hr Browning (undercoat), Reveals and Columns less than 100mm...

Mar 1, 2009