Search

What is ScheduleReader?

Forum Topic

What is it?ScheduleReaderTM is an independent standalone application for viewing XER XML and XLS project schedules. It is designed to replace the way of sharing project information as PDF files.Who is using it?All the Project Managers, Engineers, Tea...

Dec 6, 2017

Weekly Report Dilemma

Forum Topic

My new contractor's planners refuse to submit: (these are all stipulated in the contract)1. Recovery Programme2. Substantation to Claimed Progress in the weekly reports3. Procurement tracking system4. KPIs of the planned and actual works5. Any of my ...

Dec 7, 2017

Cost Loading a Schedule - Input From ?

Forum Topic

Hello Everyone,Just understand where the Cost of each activity would come from if you have to Cost Load a schedule.The BOQ of a Project would have a lumpsum quantity say for example,Concrete = 250 Cu M X 350$ / Cu M = 87,500 $.And in schedule we have...

Dec 7, 2017

Software Suggestion

Forum Topic

Hi All,I am lookingfor advice on software. Currently working on Projects within Pharma industry, we have a Roadmap developed in Excel showing all the projects between 2018 and 2023 (ususlly 5yr rolling calendar). This roadmap has all the major highle...

Dec 7, 2017

Reference-books and Typical Fragment Library

Forum Topic

Corporate project management system usually includes the databases (reference-books) of the corporate standards and templates.These templates usually include the library of typical fragments that are small projects describing creation of typical proj...

Dec 15, 2018

Total Float

Forum Topic

In my project, There are three WBS. The first and third WBS are about project start and finish procedures. And the second WBS is about all project works of different desciplines. Is there any possible technique in P6 to identify the total float based...

Dec 16, 2018

PMIS

Forum Topic

Hi All,Could any one recommend me with an excellent Project Management Information System (PMIS)? I need this for company projects and need to be used by project managers and planners.best,Muataz

Dec 16, 2018

Remaining Units Update Automatically

Forum Topic

I've imported a new project and I have started to update the progress. I've had a few problems:1. When I update the actual units on an activity the actuals are added on to the at completion instead of taken away from at completion units. In other pro...

Dec 17, 2018

Resource cost rounding

Forum Topic

Hello Vladimir,Materials in Spider have an option called Discrete Consumtion which rounds up the consumtion of the material (granted the Backload consuption is set to No).So here is my question, is there a way to do this with resources?Example: Backh...

Dec 17, 2018

User defined columns

Forum Topic

Hi,Does anyone know if its possible to create user defined columns that you can populate from drop down lists?looking to create  a columns where I can have units such as kg, tonne, m , m2 etcRegardsChris

Dec 18, 2018

Spider Macros

Forum Topic

Hello Vladimir,in the latest versions of Spider Macros have been introduced as a new functionality. There are two types of macros:Internal, from what I understand these are macros applied at the project (file) level;External, from what I understant t...

Dec 18, 2018

Baseline

Forum Topic

Every tree or two months, my Schedule Variance increase, my planner modify the baseline eachtime two reduce the variance, is it correct to do it? and if it's correct in which case we have to do it please?

Dec 24, 2018

(2019) Happy Festivities

Forum Topic

Hello everybody,Best wishes to the PP's community as our calendars approach the 2019 switch in approximately two weeks.For the planners taking christmas as a day off, merry christmas and enjoy the days out!  For all the others, planning or not, happy...

Dec 24, 2018

Schedule Percentage complete

Forum Topic

Greetings to everyone. Is there any possible technique in primavera to get all the schedule % complete for each day ? Thanks in advance.

Dec 25, 2018