Zinc Roofing
Wiki PageZinc Roofing Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Flat Roof Zinc Work = 2.3 m2/day Sloping Roof Zinc Work = 1.9 m2/day
Zinc Roofing Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Flat Roof Zinc Work = 2.3 m2/day Sloping Roof Zinc Work = 1.9 m2/day
Aluminium Roofing Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Flat Roof Aluminium Work = 2.8 m2/day Sloping Roof Aluminium Work = 1.9 m2/day
Titanium Roofing System Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Titanium roof on multiple sub‑layers. Typical composite rate of 9.5 m2/day. Inst...
Metal Roof Features Composite rates have been calculated to provide an approximation of the time elements for these ancillary parts to metal roofs. Dormer Cheeks 1.36 m2/day Flat Gutter & Coping Flashings negligible time Step Gutter & Shaped Copings ...
DownPipes 75 mm UPVC Pipes 3.3 m/hr 75 mm Cast Iron Pipes 2.1 m/hr 72 mm Aluminium Pipe System 2.5 m/hr Guttering 75 mm UPVC Gutter 3.1 m/hr 75 mm Cast Iron Gutter 2.5 m/hr 72 mm Aluminium Gutter System 2.9 m/hr Fittin...
Roof Protections Gravel & Chippings - Allow a rate of 1.4 tonnes/day for transporting and laying out solar reflective chippings.
Definition of Building Services - First Fix Environmental Control Systems This shall include the installation of all ECS equipment such as MCC's, fans and AHU's. In addition the installation of all primary and secondary ductwork and pipework sys...
Definition of Building Services - Second Fix Environmental Control Systems This shall include the installation of fan coils, EP panels and PLC panels. In addition, the insulation of all primary and secondary ductwork as well as pipework systems; leak...
Lift InstallationSequence of WorkA standard installation sequence for a "conventional hydraulic lift with 2 - 3 storeys and doors etc.Handover of lift shaft structure and associated lift machine room.Deliver all materials to site, 2 weeks.Hoisting o...
Installation SequencesIndustrial and Commercial installations usually commence when false ceilings, floorings and final decorations are substantially complete. Kitchen Hood Installations are done before false ceiling completion and kitchen equipment ...
Milestone Management In order to organise your time and work for the project you have, set up milestones and define a deliverable for each major milestone. They enable the progress of the project to be easier measured and controled. A milestone is a ...
Progress Reporting Progress reporting is a key element of project management. Reports should be issued by the Project Manager and circulated to the stakeholders on a regular basis. The following people must be included on the circulation list: Projec...
Duration estimation ala PERT Program Evaluation and Review Technique (PERT) originated in the 1950s during the U.S.N. Nautilus nuclear submarine project. PERT has terminology and concepts all its own: • Optimistic = O • Most likely = ML • Pe...
A hammock task is dependent on external dates for its start and finish dates and, ultimately, its duration. The name, hammock task, is derived from the way a hammock's shape is determined by the distance between the points to which it is attached. Cr...
What is Trending ? How does it Work ? Incremental measurement of progress over short or long periods of Time Comparison of incremental planned progress with incremental actual progress Identifies all areas where shortfall in progress occurs Quantifie...
Deltek Open Plan is an enterprise-class project management solution for medium to large/multiple projects. Details: [[http://tinyurl.com/ple5pz]]
Common Brickwork, by Machine (no/hr) Hole depth (mm) --> 0-75 75-125 125-250 250-375 375-500 Ne 100 cm2 - 16.6 7.69 5.26 4.00 100-250 cm2 - 12.5 5.88 4.00 2.94 250-500 cm2 - 10.0 5.00 3.33 2.50 500-100 cm2 - 8.33 4.17 2.78 2.08 Common Bri...
PaintingTask / DescriptionSlow Ave Fast Units Prepare Walls- 14.2 - m2/hr Prepare Doors- 12.5 - m2/hr Prepare Door Frames- 25.0 - m/hr Burn Off / Heat Strip Paintwork- 1.1 - m2/hr Internal Timber, 1 coat primer before fixing, generall...
Strip Existing Wallpapers (3 layers) 5.00 m2/hr Burn Off/Heat Strip Paintwork 1.00 m2/hr Chemically Strip Paintwork 1.30 m2/hr Prepare walls 14.20 m2/hr Prepare door frame 25.00 m/hr Prepare door 12.50 m2/hr