Hand Fill & Compact
Wiki PageLoose from side of excavation, including compaction (m3/hr)... Material Ne 100m 100-200mm 200-300mm exc 300m Loose Sand/Soil 0.85 1.02 1.28 1.69 Clay/Heavy Chalk 0.77 0.92 1.16 1.56 Hoging 0.81 0.97 1.20 1.61 Hardcode 0.71 0.84 1.06 1.41
Traffic Decking
Wiki PageInstallation of temporary traffic decking, consisting of steel beam decking and concrete panels. A typical rate of = 1.6 m2/hr.
Dewatering
Wiki PageTo setup a cofferdam dewatering system, including boring, pump installation and outflow pipework and drainage tanks etc, typical rates are...Small 2 hole system, for an overrun tunnel, with a single drilling rig takes about 7 - 10 days to get up and ...
Instrumentation
Wiki PageA typical rate of 3 days per instrument can be used to calculate detailed ground monitoring scenarios.
Grouting
Wiki PageVertical Grout Curtain Application of grout curtain. A typical rate of 6.20 hrs/m run.
Rail Grab
Wiki PageMachine Rail Mounted Hydraulic Grab Rate of 30 - 50 m3 of sand per hour (dependant upon depth), with 1.5 m3 made (2.0 m3 bucket) with each machine lift. Giving a required lift rate of 2.4 mins. A rate of 37 m3/hr (per rig) was achieved on HK Station ...
Crane Grab
Wiki PageTender rates are often quoted as between 20 and 25 m3/hr. With adequate supervision and sufficient loose spoil material supplied to the crane drop area, these rates can easily be increased. Grabs mounted on crawler cranes, rates depend on... Depth of...
Hydraulic Excavator
Wiki PageTractor with backactor, Massey Ferguson or JCB.3 has a 0.3 m3 bucket. Smaller 360 degree excavator has a 0.4 m3 bucket. JCB.6D, Liebherr 400, Hymak 580 or typical 360 degree machine has a 0.5 m3 bucket. 360 degree excavator machine has a 0.6 m3 bucke...
Material Weights
Wiki PageWagon sizes and tonnage capacities vary and should be taken into consideration. Rock = 2.5 T/m3 Concrete = 2.4 T/m3 Landfill / CDG = 1.9 T/m3 Sand = 1.8 T/m3
Ground Excavation
Wiki PageGround Excavation Rates (m3/hr):Ground TypeBucketBulk WorksBasementsTrenchesSmall & DeepSand/Soil0.3m38.78.07.18.4> 0.4m328.515.425.010.0 0.5m350.020.028.613.3Gravel0.3m37.16.96.14.5 0.4m325.914.322.28.7 0.5m340.018.128.611.1Clay/Chalk0.3m37.16.56.14...
Excavate & Load
Wiki PageExcavate Spoil Heaps and Load to Transport (m3/hr): Material0.6 m30.8 m31.0 m31.2 m3Sand/Soil20.025.630.335.7Gravel20.425.631.337.0Clay/Chalk18.523.227.833.3Boulder Clay16.921.324.430.3Note:0.6m3, 0.8m3, 1.0m3 and 1.2m3 are excavator bucket capacity....
Spoil By Barge
Wiki PageRemoval / Transportation Of Spoil By Barge: The size, getting material to the facility, location and movement restrictions of the barge loading facilities are critical to production. A 2,000 m3 flat bottom barge, could easily be loaded 1.5 times per ...
Spoil By Conveyor
Wiki PageRemoval / Transportation Of Spoil By Conveyor: The size and location of the conveyor are critical to production and should be sized according to the most critical peaks in excavation. There are the following parameters to select... Max excavation per...
Elevated Watercourse
Wiki PageModification of an existing 6 m high elevated canal. Normal canal is 12 m in width, to allow single passing on bridge/aqueduct structures, a 5.5 m minimum width is required. Normal depth of water is 1.3 m. Some 4 number "V" shaped piers on 1,200 mm b...
Floating Track Slab
Wiki PagePre-cast concrete blocks that support standard steel tracks. They are used to reduce noise and vibration as the pre-cast track slab blocks are placed on resin pads (4 no per unit), held in place by fixed side and end restraint blocks. Side restraints...
Asphalt Waterproofing
Wiki PageAsphalt coatings to prepared concrete surfaces, usually undertaken with a 3 man gang. Horizontal Surfaces = 210 m2/wk Vertical Surfaces = 85 m2/wk
Bituminous Waterproofing
Wiki PageBrush applied coatings (tretol etc) to prepared concrete surfaces. A two coat application = 5.0 m2/hr A three coat application = 3.5 m2/hr Sheet materials (bituthene etc) fixed to prepared concrete surfaces. Horizontal Surfaces = 4.0 m2/hr Vertical S...
Polythene Waterproofing
Wiki PagePolythene Sheeting Sheet materials (DPC/DPM's etc) fixed to prepared concrete surfaces. Horizontal Surfaces = 20.0 m2/hr
Bentonite Waterproofing
Wiki PageSheeting to be installed and covered over immediately in order to prevent drying out, carried out with a gang of at least 3 people. Horizontal Surfaces = 25.0 m2/hr Vertical surfaces = 15.0 m3/hr