Mediation

Wiki Page

Mediation is a method of resolving disputes in which a third party, the Mediator, facilitates a process designed to assist the parties in reaching their own voluntary solution and agreement. Mediation differs from Litigation, Arbitration or Adjudicat...

Feb 5, 2009

Work Package

Wiki Page

The work package is the lowest level of each branch of the WBS and is usually determined by the lowest level of cost collection. A unique WBS field is assigned to each work package. Work packages include detailed activities and milestones that are us...

Feb 5, 2009

Deep Compaction

Wiki Page

Essentially required in order to reduce expected ground settlement and to protect underground utilities / structures etc.Deep compaction by 350 mm dia Vibroflot, 3 m centres in sand.Working on 12 hour basis, a vibroflot will achieve an output of 3-4,...

Feb 6, 2009

Compact & Consolidate

Wiki Page

Compact & Consolidate using Vibratory Roller or compactor. Sand 31.25 m2/hr Soil 58.82 m2/hr Clay 55.56 m2/hr Hardcore 38.46 m2/hr Ash 57.85 m2/hr

Feb 6, 2009

Cofferdam Works

Wiki Page

Soil Mix Wall Three auger machine drilling and mixing cement into three cores. H-piles dropped into two, then machine moves along by two holes. An average output was 4 - 5 m/day.

Feb 6, 2009

Strutting

Wiki Page

Strutting To install simple horizontal heavy duty strutting, a typical rate of 2 days per strut/gang is reasonable. To install diagonal slab/roof cross-brace strutting, a typical rate of 6 days per strut/gang is reasonable. To remove these struts, al...

Feb 6, 2009

Multiple Bell Ground Anchors

Wiki Page

Multiple Bell Ground Anchors Often used in London Clay. Uncased, 10 m long 2.0 no/day Top Cased type, 15 m long 1.0 no/day Anchor Stressing 2.0 no/day

Feb 6, 2009

Removable Ground Anchors

Wiki Page

Removable Ground Anchors Recent innovation of "removable" ground anchor system. Steel cables are doubles up and threaded over a roller at the anchor end. Once de-stressed, they can be pulled out. 1 rig can achieve... Drill 30 m shaft 7.0 hrs Install ...

Feb 6, 2009

Slurry Mix Wall

Wiki Page

Slurry mix wall (for noise restrictions/obstructions) grab excavation to full depth, fill with cement or bentonite mix, drop and hold sheet piles in place.Excavation 1 panel (4.5 m long on plan) with grab and crane.Excavate 1 panel in 2 days + 1 day ...

Feb 6, 2009

Sheet Piling

Wiki Page

Sheet Piling On reclamation, sand fill, sheet piling by crane and drop hammer, vibro hammer or diesel hammer.A rate of 20 - 25 No/day to 20 to 35 m deep.1 no = 0.4 m wide on plan and 6 m long.Therefore 8 - 10 m/day per rig is achievable.On more diffi...

Feb 6, 2009

Hand Fill & Compact

Wiki Page

Loose from side of excavation, including compaction (m3/hr)...   Material Ne 100m 100-200mm 200-300mm exc 300m Loose Sand/Soil 0.85 1.02 1.28 1.69 Clay/Heavy Chalk 0.77 0.92 1.16 1.56 Hoging 0.81 0.97 1.20 1.61 Hardcode 0.71 0.84 1.06 1.41

Feb 6, 2009

Traffic Decking

Wiki Page

Installation of temporary traffic decking, consisting of steel beam decking and concrete panels. A typical rate of = 1.6 m2/hr.

Feb 6, 2009

Dewatering

Wiki Page

To setup a cofferdam dewatering system, including boring, pump installation and outflow pipework and drainage tanks etc, typical rates are...Small 2 hole system, for an overrun tunnel, with a single drilling rig takes about 7 - 10 days to get up and ...

Feb 6, 2009

Instrumentation

Wiki Page

A typical rate of 3 days per instrument can be used to calculate detailed ground monitoring scenarios.  

Feb 6, 2009

Grouting

Wiki Page

Vertical Grout Curtain Application of grout curtain. A typical rate of 6.20 hrs/m run.

Feb 6, 2009

Rail Grab

Wiki Page

Machine Rail Mounted Hydraulic Grab Rate of 30 - 50 m3 of sand per hour (dependant upon depth), with 1.5 m3 made (2.0 m3 bucket) with each machine lift. Giving a required lift rate of 2.4 mins. A rate of 37 m3/hr (per rig) was achieved on HK Station ...

Feb 6, 2009