Excavate and Remove

Wiki Page

 Excavate and RemoveTask / DescriptionSlow  Ave  Fast   Units Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil14.5 20.0 25.6  m3/hr Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds15.2 20.4 25.6  m3/hr Excavate Spoil Heaps to Tr...

Oct 14, 2010

Termination of the Contract

Wiki Page

Termination of the contract For termination of a contract due to default by the Contractor, FIDIC 4th Edition provides remedies for the employer in Clause 63.1 which, save for a fairly common provision relating to the contractor’s bankruptcy, liquida...

Oct 18, 2010

Qatar’s Guild Interest Group Meeting No 3 (Doha)

Event

Next event...The next meeting of the Qatar Guild has been scheduled!This meeting will be a special event involving a private presentation of the Qatar rail project using the hi tech presentation facility at the Lusail Offices. The meeting will start ...

May 7, 2011

Concrete Finishing

Wiki Page

Concrete FinishingTask / DescriptionSlow  Ave  Fast   Units Surface Finishing, Steel Float By Hand9.2 13.9 25.0  m2/hr Surface Finishing, Wood Float By Hand11.7 17.2 29.4  m2/hr Surface Finishing, Power Float13.9 20.8 37.0  m2/hr Surface Finishing, L...

Jul 19, 2011

Ceiling Finishes

Wiki Page

Ceiling FinishesTask / DescriptionSlow  Ave  Fast   Units Suspended Ceilings, office situations-  2.6 3.5  m2/hr Suspended Ceilings, First Fix-  0.7 -   m2/hr Suspended Ceilings, Second Fix-  1.2 -   m2/hr

Jul 19, 2011

Carpentry Final Fixing

Wiki Page

Carpentry Final FixingTask / DescriptionSlow  Ave  Fast   Units Windows, Softwood, 3.0-7.0m20.6 0.4 0.3  hrs/no Windows, Softwood, 7.0-10.0m21.3 0.9 0.6  hrs/no Windows, Hardwood, 1.0-3.0m20.4 0.3 -   hrs/no Windows, Hardwood, 3.0-7.0m20.7 0.5 0.4  h...

Jul 19, 2011

Carpentry Carcassing

Wiki Page

Carpentry CarcassingTask / DescriptionSlow  Ave  Fast   Units Windows, Timber Frames for Bricklaying1.1 0.5 0.1  hrs/no Windows, Drill, Screw & Plug extra over0.3 0.1 -   hrs/no Door Frames, Softwood, 1.0-3.0m2-  0.2 -   hrs/no Door Frames, Softwood,...

Jul 19, 2011

Carpentry & Joinery

Wiki Page

Carpentry & JoineryTask / DescriptionSlow  Ave  Fast   Units Formwork to Soffit of Manhole-  1.8 -   m2/hr Formwork to Walls of Manhole11.2 14.2 20.2  m2/hr Formwork to Road Edges, straight-  7.7 -   m/hr Formwork to Road Edges, curves-  6.2 -   m/hr

Jul 19, 2011

Bulk Excavation

Wiki Page

Bulk ExcavationTask / DescriptionSlow  Ave  Fast   Units Excavation Bulking Factor, Sand/Soil-  15.0 20.0  % Excavation Bulking Factor, Gravel-  33.0 -   % Excavation Bulking Factor, Clay/Chalk-  40.0 -   % Excavation Bulking Factor, Boulder Clay-  4...

Jul 19, 2011

Basement Excavation

Wiki Page

Basement ExcavationTask / DescriptionSlow  Ave  Fast   Units Hydraulic Excavator, 0.3m3 bucket, Sand/Soil - Basement Works6.4 8.0 9.4  m3/hr Hydraulic Excavator, 0.3m3 bucket, Gravel Beds - Basement Works5.5 6.9 8.1  m3/hr Hydraulic Excavator, 0.3m3 ...

Jul 19, 2011

Bell Ground Anchors

Wiki Page

Bell Ground AnchorsTask / DescriptionSlow  Ave  Fast   Units Uncased Anchors, 10m long-  2.0 -   no/day Top Cased Anchors, 15m long-  1.0 -   no/day Anchors stressing-  2.2 -   no/day

Jul 19, 2011

Bored Piling

Wiki Page

Bored PilingTask / DescriptionSlow  Ave  Fast   Units Cycle Time, 5-20m deep8.0 4.0 4.0  days/no Cycle Time, 20-40m deep10.0 8.0 -   days/no Cycle Time, 40-70m deep25.0 10.0 -   days/no Cycle Time, 70-90m deep45.0 25.0 -   days/no Cycle Time, 90-135m...

Jul 19, 2011

Lean Design – there's more to BIM than technology

Event

LEAN DESIGN - THERE'S MORE TO BIM THAN TECHNOLOGYWHEN: Tuesday 1 November 2011 1500-1700[[wysiwyg_imageupload:649:]]WHERE: The Swan, 66 Bayswater Road, Paddington, London W2 3PHRESERVE A SEAT: please use the signup link aboveIf you change the technol...

Aug 31, 2011

Qatar’s Guild Interest Group Meeting No 2 (Doha)

Event

Welcome to Qatar’s Guild Interest Group for the Guild of Project Planning, Controls & Delivery (GPPCD).[[wysiwyg_imageupload:375:]]We would like to invite you to the second small informal event to help planners meet, share knowledge and say hello.Whi...

Apr 1, 2011

BIM Collaborative Interest Group Meeting No 3 (London)

Event

We are keen to meet and discuss Building Information Modeling (BIM) with members of our community, and that includes all planners. This will be is our 3rd meeting for this Guild Interest Group within the Guild and we will take a look at some case stu...

May 29, 2011

Qatar’s Guild Interest Group Meeting No 4 (Doha)

Event

Dear All, At the last meeting we talked about the different subjects members would like presentations and discussions on in the future.  One subject that was bought up was BIM’s and how they will relate to planning.  As it happens through my day job ...

May 29, 2011

Footing formwork

Wiki Page

ActivityTASKSTask - UOMLabor (L) - Carpenter (Mandays)Labor (L) - Helper (Mandays)Material (M)Material (M)Material (M)Footing formworkFooting - Shuttering & Providing SupportSqm0.8 Mandays/10Sqm1.5 Mandays/10SqmMS Wall Form Panel - 1250 x 500 : 16Nos...

Jun 6, 2011

Raft formwork

Wiki Page

 ActivityTASKSTask - UOMLabor (L) - Carpenter (Mandays)Labor (L) - Helper (Mandays)Material (M)Material (M)Material (M)Raft formworkRaft - Shuttering & Providing SupportSqm0.71 Mandays/10Sqm1.41 Mandays/10SqmMS Wall Form Panel - 1250 x 500 : 16Nos/10...

Jun 6, 2011

Walls formwork

Wiki Page

 ActivityTASKSTask - UOMLabor (L) - Carpenter (Mandays)Labor (L) - Helper (Mandays)Material (M)Material (M)Material (M)Walls formworkWalls (Any Thickness), Including Buttresses - Shuttering & Providing Support - Up to 3.5m HeightSqm2.22 Mandays/10Sqm...

Jun 6, 2011