How to define Resource Productivity in Primavera P6 and create schedule
BlogWhen create a schedule, we can based on Resource Productivity to estimate duration.For example:We have a team which can cast 10 m3 of concrete per day (This is Productivity)We have an Foundation which take 100 m3 concrete.Duration of Foundation activ...